Drainage Exceedance Route Questions Checklist
Help an owner ask for the exceedance route as a design output, understand what it crosses, check it against the levels as built, and record it so later work does not quietly remove it.
7 sections · 42 planning prompts · educational owner-side preparation
https://www.builddesignhub.com/checklists/drainage-and-site-discussion/drainage-exceedance-route-questions · Build Design Hub — educational planning resource. Requirements vary by project and location.
Scope
What this checklist covers
The preparation ground these prompts walk through.
- Asking for the route to be named and drawn rather than assumed
- Every feature on the site that holds, infiltrates or collects water
- What each route crosses on its way
- Checking routes against the levels as built rather than as drawn
- The overflow that is never seen working
- Recording the route and protecting it from later work
Audience
Who this checklist is for
- Owners reviewing a surface water proposal for their property
- People who have inherited a drainage arrangement they did not commission
- Householders changing levels, kerbs, fences or thresholds on a drained site
- Anyone building a property record of what is buried and what must stay clear
Timing
When to use it
- Asking for the exceedance route during design or at handover
- Working out what an existing arrangement does when it is exceeded
- Checking a route against the levels that were actually built
- Recording a route so later work does not remove it
- Preparing the instruction given to contractors and gardeners
Limits
When it is not sufficient
This is general planning preparation. These situations need a qualified professional, and often the relevant authority.
- Determining where exceedance flow should go, which is a design output
- Establishing rainfall assumptions, capacities or design events
- Deciding whether any route is adequate for your site
- Replacing design by a qualified drainage professional
The checklist
Work through the sections
Tick the boxes on paper or on screen — nothing is stored, so print the page if you want to keep your marks.
1.Asking for the route to be named and drawn
This is one output of a drainage design that is almost never handed over. Asking for it is the whole of the first step.
Ask where water is expected to go when the arrangement is full and rain has not stopped, and ask for that answer in writing.
Phrasing it as a question about a specific condition gets a specific answer, where asking about drainage generally does not.
Where exceedance flow goes on a particular site is a design output produced by qualified professionals against assumptions that vary by location.
Ask whether that route has actually been drawn, or whether it has been assumed from how the ground happens to fall.
An undrawn route is chosen by the finished levels rather than by anybody holding the design, which is the point of asking.
Record that this route is part of the design rather than an accident, so it is treated as something owed to you rather than a courtesy.
Owners often assume the question is unreasonable, and writing down that it is a design output makes it easier to press.
Establish who is responsible for producing and handing over the route, and when in the project that would happen.
Something owed by nobody in particular is produced by nobody, and naming the responsibility early is what prevents that.
Where the arrangement already exists, ask whoever installed it, the developer or a management company whether any record of the route exists.
For an inherited arrangement the honest answer is often that it was never recorded, and that is itself worth establishing.
Note that leaving the route undrawn does not remove the surplus water, it only relocates it to wherever the levels send it.
Understanding that the water arrives regardless is what makes this question feel worth asking rather than theoretical.
2.Every feature that holds, infiltrates or collects water
One site can have several arrangements, each with its own secondary route. Listing them is what makes the question answerable.
List every arrangement on the site that holds, infiltrates or collects water, including anything that looks like ordinary landscape.
A drainage feature shaped like a dip or a planted hollow tends to be treated as landscape, including by the owner.
For each one, put the same question: when this is full and rain continues, where does the next of it go, and has anybody drawn that.
Asking feature by feature is what stops the answer being a general reassurance about the site as a whole.
Note that the secondary route takes a different physical form in each arrangement, which is part of why it is easy to overlook.
Looking for one kind of thing across a whole site means missing the ones that take another form entirely.
Include any surface built to let water through, since it has a store beneath it with its own arrangement once that store is full.
A permeable surface is easily left off a list of drainage features because it looks like a drive.
Include roofs, gutters and anything holding water at high level, and ask what happens at each once its capacity is reached.
A roof that finds its own route takes it at the lowest point of the perimeter, which nobody chose.
Where you cannot establish what a feature is, record it as unidentified and ask about it specifically rather than leaving it out.
The unidentified feature is the one most likely to be built over, precisely because nobody could say what it was.
3.What each route crosses on its way
Where the water goes matters, and so does what it passes on the way there. This is the part an owner can walk.
Walk each route on the ground and write down what it passes, rather than reading it from a drawing alone.
Walking a route reveals kerbs, planters and thresholds that a drawing of the buried arrangement does not show.
Note whether any route passes a doorway, a threshold, an airbrick or any other low-level opening into a building on the site.
A route that ends at a threshold is the outcome this whole question exists to identify, and it is visible from the ground.
Note whether any route passes over, along or towards anything that is holding a level, and raise each of those specifically.
Water arriving at retained ground is a question for more than the drainage designer, and it is worth flagging early.
Water arriving at or crossing retained ground is a question for a qualified engineer as well as for the drainage designer.
Note whether any route crosses a boundary, or would deliver water onto ground belonging to somebody else, and mark where it does.
A route across somebody else's ground is a different proposition and may involve obligations settled before anything is built.
Where water would reach neighbouring land, obligations vary by location and should be confirmed with a suitably qualified adviser.
Note whether a route crosses a parking area, a planted feature or anything that was not intended to receive that quantity of water.
A planted feature taking the surplus from a whole site was probably not sized for it, and that is worth asking about.
Note what sits beneath or beyond the point where any overflow discharges, including a wall face, a path or a terrace.
Whatever is below an overflow takes the wash of every event the primary route has missed, and nobody chose that position.
4.Checking against the levels as built
The route runs over the same ground as everything else, and that ground changes after the drainage is drawn.
Ask whether the route was checked against the levels that were actually built rather than the levels that were originally drawn.
The two differ more often than owners expect, and the route depends entirely on the ones that exist.
Walk the route and note anything added since the levels were set, including a kerb, a planter, an edging or a raised bed.
Each of those can dam a route without anything anybody would call drainage having been touched.
Note anywhere a kerb, edging or upstand has been removed or lowered, since a route can depend on something being there.
Removal is as consequential as addition, and it is far less likely to be remembered by anybody.
Note any fence, gate or wall built across the route, including anything that would hold water back or divert it sideways.
A fence line built along a boundary can sit exactly across a route, and it is put up by somebody who has no idea.
Note where any surface has been relaid or a threshold raised since the arrangement was built, and when that happened.
Resurfacing is treated as a finish decision and it changes levels, which is the one thing the route depends on.
Make a habit of walking the route again after any work at the property, including work that had nothing to do with drainage.
The changes that matter here are almost always made during unrelated jobs by people who were never told.
5.The component nobody sees working
A secondary route only operates when everything else has stopped. That single property is what makes it hard to look after.
Note that an overflow is not seen working, is rarely checked, and that a silted one looks identical to a clear one on a dry day.
Understanding why it is neglected is what makes an owner treat it deliberately rather than assuming somebody else will.
Ask whether any overflow is independent of the primary route, so a blockage in one would not disable both.
An overflow sharing a route with the outlet it is protecting is disabled by the same blockage.
Ask whether any overflow discharges somewhere a person would actually notice it running, and record exactly where that point is.
A concealed discharge gives up the warning that is half the point of having the overflow at all.
Ask how the secondary route is inspected given that it only acts once something else has failed, and who is expected to do it.
An inspection regime for something never in use has to be deliberate, because nothing will prompt it otherwise.
Record that an overflow which has started running is doing its job and reporting on the primary route, and note the date it happened.
The thing worth investigating is the primary outlet, and the thing worth recording is that the secondary route is still clear.
Ask whether any part of the secondary route can be reached and cleared without specialist help, and what clearing involves.
Something that cannot be reached will not be cleared, however clearly the obligation is written down.
Do not open or enter any chamber or structure to reach an overflow; ask whoever is responsible for the arrangement.
6.Reading a route by what is absent
Some of the most useful observations here are of things that are no longer happening. They are made at the property rather than on paper.
Note anywhere water stands above the level an opening or overflow was set to hold, and photograph it with the date.
Water held above the level something was set to hold is a report that the opening is no longer taking it.
Note any washed strip, staining or growth beneath an opening that is now dry, and record where it is.
A mark showing that something ran once and no longer does is the classic evidence of a route that has gone.
Photograph and report any of these before cleaning them away, since the mark itself is the evidence rather than simply untidiness.
Making good removes the only sign that a secondary route has stopped being available.
Go out during heavy rain and note where water actually runs on the site, and whether it matches what you were told.
The route in use is observable only in the conditions that bring it into use, so the visit has to be deliberate.
Record what you observe each time with a date, so the same route can be compared across several storms and several years.
A single observation describes one storm, and the useful picture is built from several of them.
Take the observations to whoever is responsible as a description of what you saw rather than as a conclusion about what has failed.
A description invites an examination, whereas a conclusion invites agreement or disagreement with your own diagnosis.
7.Recording the route and protecting it
A recorded route survives the next change of ownership and the next landscaping contract. An unrecorded one does not.
Ask for the route to be recorded in a form you can keep, showing where it runs and where it discharges.
Unrecorded, the route is indistinguishable from ground that happens to fall that way and is removed by the first improvement.
Write a plain-language version saying where the route runs and what must not be built, planted or stored across it.
The person who eventually needs this is a landscaper or a fencing contractor, not somebody who reads drainage drawings.
Put that note into whatever you give any contractor working outdoors, including work that has nothing to do with drainage.
The route is removed by unrelated work, so the note has to travel with every job rather than with drainage jobs.
Tell whoever maintains the garden which ground has to stay as it is, including levels, edges and anything that must not be built up.
Maintenance changes levels gradually, a barrow at a time, and nobody involved would describe it as changing the drainage.
Keep the route record with the property paperwork and decide now that it will be handed to a buyer at the point of sale.
Handing it on is the only way the route survives, and it happens only if the decision was taken long beforehand.
Update the record whenever levels, surfaces, fences or thresholds change anywhere near the route, noting what changed and when.
A record describing levels that no longer exist is worse than none, because it will be trusted.
Preparation
Documents and information to gather
Having these to hand usually makes the first conversation shorter and more useful.
- Any drainage record or drawing showing arrangements on the site
- A written statement of where exceedance water is expected to go
- A plan of the site with each route walked and marked on it
- Photographs of what each route passes, including thresholds and boundaries
- Your own dated observations of where water runs during heavy rain
- A dated list of level, surface and boundary changes made since the arrangement was built
Records
Decisions to record before work begins
Write these down in your own words, with the date, so everyone is working from the same version.
- Which arrangements on the site hold, infiltrate or collect water
- Where the route for each is said to run, and whether it was drawn or assumed
- What each route crosses, including thresholds, boundaries and retained edges
- What has changed on the site since the levels were set
- The wording of the note given to contractors and to whoever maintains the garden
- That the route record will be handed to a buyer at the point of sale
Professional review
Questions to discuss with qualified professionals
Bring these to the relevant qualified professional, supplier or authority. Requirements vary by project and location.
- Where is water expected to go when each arrangement is full and rain continues?
- Has that route been drawn, or has it been assumed from the finished levels?
- Was it checked against the levels as built rather than as originally designed?
- What does each route cross on its way, and what does it discharge onto?
- Is any overflow independent of the primary route it is protecting?
- Does any overflow discharge somewhere a person would notice?
- How is the secondary route inspected, given it is never in use?
- Can the route be recorded in a form that stays with the property?
Blind spots
Commonly overlooked items
- That the route is a design output rather than a courtesy to ask for
- A drainage feature shaped like an ordinary dip or planted hollow
- A kerb removed, or a planter added, across a route nobody recorded
- A fence line built along a boundary that sits across a route
- That an overflow which has started running is reporting on the primary outlet
- Staining or a washed strip beneath an opening that is now dry
- That the note has to reach contractors doing entirely unrelated outdoor work
What this checklist does not do
- Where exceedance flow goes on a particular site is a design output produced by qualified professionals, and nothing here determines it.
- No rainfall assumption, capacity or level is stated here and none can be inferred; those belong entirely with the drainage designer.
- Where a route would deliver water onto neighbouring land, obligations vary by location and should be confirmed with a suitably qualified adviser.
- Observations of staining, standing water or a dry opening are worth reporting rather than cleaning away, and are not diagnoses.
More preparation
Related checklists
Inspiration
Related Ideas Library pages
Design directions to explore once the preparation is done.
Go deeper
Related Build Design Hub guides
Explanatory planning guidance behind the decisions on this page.