Who this guide is for
- Homeowners planning an extension whose roof meets an existing wall
- Renovators cutting a new opening into a cavity wall
- Anyone commissioning work that adds a support or a bearing into an outer leaf
- Owners considering filling an existing cavity
- Self-builders coordinating trades across an existing wall
The rule underneath all of them
The masonry cavity wall record states the general case once and then leaves it. Wherever the void stops or is bridged, whether by a lintel, a change of construction, a floor bearing or an abutting roof, the drainage arrangement has to be re-made. The tray record adds that a tray without an exit does not drain and that outlets without a tray above them drain nothing, so the pair works only together.
What makes this an alteration question rather than a construction one is that all of these interruptions can be created after the wall exists. Nothing about the original wall changes; a new line is introduced across the void, and the water that used to run past that line now arrives at something.
- An interruption is any line where the void stops or is bridged
- Interception and discharge are one arrangement, not two options
- The interruption can be created long after the wall was built
- The wall itself gives no warning that a new line has appeared
An extension roof arriving against a wall
This is the most common of them, and the records describe why it is also the most awkward. An abutment needs a tray inside the wall as well as flashings outside it, and the tray belongs to the masonry trade while the flashing belongs to the roofer. The junction between their two pieces of work is inside the wall where neither can see it.
The abutment record adds a timing problem on top of the ownership one. Provision for the concealed tray has to be made while the wall is being built, by a trade that will have left before the roof is weathered, and where it is missed the remedy involves taking part of the wall apart again. Where the wall already exists, as it does on an extension, that remedy is the starting point rather than the fallback.
The record also asks a question an owner can put directly: has a tray been provided at this abutment, and can its discharge points be seen from outside the building? The weeps have to discharge above the cover flashing, which means two trades have to agree a level that neither of them controls alone.
A new opening
Cutting an opening into a cavity wall interrupts the void on every side at once. The cavity wall record describes the head as needing interception and outlets, the jambs as needing a closer that carries no water across, and the sill as having to throw water clear of the leaf below. The frame is normally fixed to the inner leaf, so the seal between frame and closer is also where the wall's air line passes.
The tray record then names the failure that follows from doing half of it. Without stop ends, a tray discharges into the wall beyond the ends of the opening, so damp appears to one side of a window rather than above it and is diagnosed as something else entirely. The window is usually blamed, and the window is usually not involved.
- The head, the jambs and the sill each interrupt the void differently
- Stop ends decide whether the interception works at its ends
- Damp at a reveal is routinely attributed to the window
- The air line and the water path meet at the same closer
A support angle or a new bearing
Any line where the outer leaf stops carrying itself and hands its weight back to the structure is also a line where the void is closed. The veneer record makes the point generally: every place the leaf is carried is a place the void is closed, so support and drainage are the same detail, and support provided without interception and open outlets below concentrates water at exactly the point where the wall is least able to shed it.
The infill wall record adds a setting-out consequence. Every support angle, nib or floor edge crossing a cavity is an interruption, and water travelling down inside the wall arrives at it, so where trays are provided their stop ends and drainage openings have to coincide with the support rather than with the drawing grid. A tray drawn to a grid and a support built to a structure are two different lines.
Filling a cavity that already has interruptions
An insulation upgrade is not usually thought of as a drainage alteration, and the records treat it as one. Trays over lintels, at abutments and at the base were detailed to discharge into an open void; after filling they discharge into a material. That is why the presence, continuity and stop ends of those trays are among the first things a survey looks for.
The retrofit record is also clear about what a survey finds. Existing walls frequently have interruptions with no tray at all, which is a survey question rather than an assumption, and introducing fill both changes what any existing trays are dealing with and reveals whether they were ever installed. It adds that vents, flue ways, ducts, boxes and tray ends each become either a place fill escapes into or a designed air path that is blocked, and that none of these is drawn on an ordinary existing house.
- Interception that discharged into a void now discharges into a material
- Whether trays exist at all is established by survey, not assumed
- Vents, flues and ducts crossing the void are found by inspection
- Later access for drainage remedial work is reduced by the fill
Why the requirement appears on nobody's drawing
Each of these alterations is commissioned as something else. An extension is a room; an opening is a view; a support is a structural item; a fill is an energy measure. The interruption is a by-product, and the record's observation is that because no single package owns cavity interruptions, the tray is frequently the item that nobody realised was needed.
That is why the published design questions are framed as an audit rather than as a specification. Where in this wall is the cavity interrupted, and has each of those interruptions been reviewed? Where two separate runs meet, which one laps over the other and in which direction does the water travel? Both are questions to ask of the whole wall, including the parts nobody is altering.
What this guide is not about
It is worth stating the boundary explicitly, because the neighbouring failure looks similar from inside the room. This guide is about a requirement being created: a new line across the void that water now arrives at, needing interception and a way out. It is not about a connection being made by accident across a void that is otherwise intact, which is the subject of the companion guide on accidental bridges.
The distinction matters for diagnosis. If the void was interrupted and nothing was provided, the answer is an arrangement that was never built. If the void is uninterrupted and something is carrying water across it, the answer is a connection that should not exist. Those lead to different investigations and different remedies, and an alteration can produce both at once.
Before an alteration that touches a cavity wall
- 1Ask whether the proposed work interrupts or bridges the cavity anywhere
- 2List every interruption the work creates, including ones nobody would call cavity work
- 3Ask who is providing the interception at each one, in writing
- 4Ask which trade will be on site when it has to be built in
- 5Check that stop ends are shown on the drawing rather than assumed on site
- 6Check that outlets sit where what is collected can actually leave the wall
- 7Ask where two separate runs meet and which laps over the other
- 8Ask whether the discharge points can be seen from outside once the work is finished
- 9Where a roof abuts, establish who agrees the level the weeps discharge above
- 10In an existing wall, establish by survey whether anything was provided at existing interruptions
- 11Before filling a cavity, ask what any existing interception will discharge into afterwards
- 12Ask how vents, flues and ducts crossing the void will be dealt with
- 13Record what was installed and where, before the masonry closes it
Common mistakes to avoid
- Treating an extension, an opening or a support as work that does not touch the cavity
- Assuming an existing wall already has interception at its existing interruptions
- Providing interception with no stop ends, so water is delivered beyond the opening
- Providing outlets with nothing above them, or interception with no way out
- Setting out interception to a drawing grid rather than to where the support actually sits
- Filling a cavity without establishing what the existing arrangements discharge into
- Blaming a window for damp that appeared at a reveal after an alteration above it
When to involve a professional
- Ask the designer which interruptions this work creates and how the list was arrived at
- Ask who provides the concealed interception and which package it sits in
- Ask how continuity is achieved where separate runs meet at corners, abutments and floor edges
- Ask what will stop insulation, mortar or ties from bridging above the interception line
- Ask how each run and its stop ends will be inspected before the following courses conceal them
- In an existing building, ask what evidence there is about what was installed originally
Frequently asked questions
Questions readers ask about this topic
Does building an extension really change the wall it is built against?
It introduces a new line where a roof meets that wall, and the records describe an abutment as needing interception inside the wall as well as flashings outside it. The wall was not altered in the usual sense, but water travelling down inside it now arrives at something that was not there before.
Why does damp appear beside a window rather than above it?
The cavity tray record describes this directly. Without stop ends, interception at a head discharges into the wall beyond the ends of the opening, so the damp shows at the reveals rather than over the frame and is routinely attributed to the window instead of to the arrangement above it.
Is filling a cavity an alteration to its drainage?
The records treat it as one. Any existing interception was detailed to discharge into an open void and afterwards discharges into a material, which is why the presence, continuity and stop ends of what is already there are among the first things a survey looks for before fill is placed.
How is this different from a cavity being bridged by accident?
A requirement created and a connection made are different events. Here an alteration introduces a new line across the void that water now arrives at and has to leave from. In the companion case the void is intact and something is carrying water across it that should not be there. Different investigations follow from each.
Can I tell from outside whether any of this was done?
Sometimes partly. The abutment record asks whether the discharge points can be seen from outside the building, which is a question an owner can put. What is inside the wall cannot be established that way, and the records treat it as a survey question for a qualified professional rather than something to infer from the elevation.