Who this guide is for
- Owners who have been told their building may need underpinning
- Buyers assessing a property that has been underpinned previously
- Owners comparing a specialist's proposal with a second opinion
- Anyone whose insurer or surveyor has raised foundation movement
- Owners considering deepening in order to gain space below ground
What the work actually is
Every other foundation is formed before anything stands on it, onto ground nobody is loading. Underpinning is not. The structure is already bearing, the load path is live throughout, and a new foundation is formed beneath and beside the old one so that path has to be interrupted and remade rather than established.
It is the only foundation arrangement formed under load, which is why it belongs to temporary works design as much as to permanent works design, and why it is not a scaled-up version of ordinary groundwork.
The smallest part of the work is the whole point of it
A new element formed perfectly at the right level, on sound ground, with the right reinforcement, carries nothing until the joint above it is packed. Load is handed across a dry-pack, a grout or a set of wedges between the top of the new element and the underside of the existing foundation.
Leave that joint unmade and the new element is present but idle, and the old footing arrives on it later by settling, which is precisely the outcome the work exists to avoid. When an owner asks what to watch, the honest answer is the joint and who inspects it before the excavation is backfilled.
Diagnosis first, because the causes outlive the remedy
Deepening takes an existing foundation to a different bearing level. It does not remove a tree, repair a leaking drain, undo a raised water table or consolidate fill, and each of those continues afterwards unless it is addressed on its own terms.
So the first question in the conversation is not how the work would be done but what the diagnosis of the movement is and what evidence supports it. A proposal that arrives without a diagnosis is proposing a remedy for an unnamed condition.
- Vegetation changing how much moisture the ground holds
- A drain leaking or a water regime that has changed
- Fill or made ground that has not finished settling
- Ground removed beside the footing by an earlier excavation
The alternatives it sits against
The entry names two alternatives explicitly. Ground improvement treats the soil and leaves the existing foundation where it is; this work leaves the soil and moves the foundation. Piling carries load past weak near-surface ground on slender elements, approached as a matter of bearing rather than as work beneath a standing structure.
Which of them is appropriate is a geotechnical and structural judgement. What an owner can reasonably ask is which were considered and what separated them on this building.
A fixed scheme agreed in advance is a warning
The ground at the deeper level has not been seen before the work exposes it, and what is found there can change the depth, the element and the support arrangement together. That is why an underpinning scheme is commonly written to be revisited once the ground is open.
The entry is unusually direct about the corollary: a fixed scheme agreed in advance is a warning rather than a reassurance. A proposal that cannot change when the formation is exposed has decided something nobody could yet know.
What the work changes besides the bearing
Deepening one length changes the length beside it. The un-deepened neighbour now founds at a different level, so a step exists in the foundation line where none was designed, and the wall above spans a change in bearing condition.
It also cuts through things. The horizontal damp-proof and gas barriers in and beside the existing construction are interrupted by the excavation and the new element, and making them continuous again is part of the work rather than a repair afterwards. Old drains commonly run at exactly the depth and position the work occupies.
Nothing about how it is done can be generalised
How much bearing may be absent at any moment, what holds the structure while it is, and in what arrangement the work proceeds are determined together for that structure by a qualified temporary works and structural engineer. No sequence, order or open length can be read off another building.
The record is what a future owner inherits
What the existing foundation was, what was found at formation, where each new element sits and how the joint was made are recoverable afterwards only from records. A later owner, a later extension and a later insurer all depend on that record existing, and it is worth insisting on before the work is signed off.
Questions before agreeing to deepening
- 1Ask what the diagnosis of the movement is, and what evidence supports it.
- 2Ask what investigation has been carried out into the existing foundation and the ground beneath it.
- 3Ask what alternatives were considered, and what separated them on this building.
- 4Ask whether the cause identified will still be present after the work.
- 5Ask what happens to the scheme if the ground found at formation is different.
- 6Ask who is designing the temporary support, and how that relates to the permanent design.
- 7Ask how load transfer at the pinning joint is specified and how it is verified.
- 8Ask what happens at each end, where deepened meets un-deepened length.
- 9Ask what is known about drains, services and any neighbouring foundation in the zone.
- 10Ask how the damp-proof and gas barrier lines will be made continuous again.
- 11Ask what monitoring is proposed during the work and what would cause it to stop.
- 12Ask what record of the completed work will be provided, and in what form.
Common mistakes to avoid
- Accepting a remedy before a diagnosis, when several causes produce the same symptom and most of them survive the work.
- Reading the new element as the thing that supports the building, when it carries nothing until the joint above it is packed.
- Taking a fixed scheme priced in advance as reassurance, when the ground at the deeper level has not been seen.
- Confusing deepening with ground improvement, when one leaves the soil and the other treats it.
- Forgetting the ends, where the deepened length meets ground the work did not reach.
- Treating the interrupted damp-proof and gas lines as a repair afterwards rather than part of the work.
- Letting the excavation be backfilled before anyone has inspected the joint.
- Finishing without a record of what was found at formation and where each element sits.
When to involve a professional
- Whether deepening is the answer to any particular movement is a determination for a structural engineer; diagnosis comes before remedy.
- Work beneath a loaded structure is temporary works design carried out by qualified engineers and contractors, and is not an owner activity.
- No sequence, bay arrangement, open length, depth or support scheme is stated or implied here, because none can be transferred from one building to another.
- Deepening beside an adjoining building carries obligations that vary by jurisdiction and are verified against local requirements before any work is planned.
- What is packed at the pinning joint, and how, is specified by the engineer for that joint rather than chosen on site.
Frequently asked questions
Questions readers ask about this topic
Will underpinning stop my building moving?
It takes an existing foundation to a different bearing level, and the reference entry states plainly that it does not by itself resolve why movement happened. Trees, drains, changed water regimes and made ground continue afterwards unless each is dealt with separately.
What is the pinning joint and why does it matter?
It is the packed joint through which load passes from the old foundation to the new one. Until it is made, the new element carries nothing and the old footing would arrive on it later by settling, which is the outcome the work exists to avoid.
Should the scheme be fixed before work starts?
The ground at the deeper level is not seen until the excavation reaches it, and what is found can change the depth, the element and the support together. The entry describes a scheme written to be revisited on site, and calls a fixed one a warning.
How is this different from ground improvement?
Ground improvement treats the soil and leaves the existing foundation where it is. Deepening leaves the soil and moves the foundation. They answer the same inadequate bearing from opposite directions, and which suits a building is a geotechnical and structural judgement.
What records should I get at the end?
What the existing foundation was, what was found at formation, where each new element sits and how the joint was made. None of it can be seen afterwards, and a later owner, extension or insurer will be working from that record alone.