Who this guide is for
- Owners planning a single-storey or two-storey extension to an existing house
- Self-builders adding to a building whose foundations are undocumented
- Buyers assessing an extension that has cracked at its junction with the original house
- Owners adding a conservatory, porch or garden room against an existing wall
- Anyone briefing a structural engineer on an addition rather than a new build
You are joining to something nobody has records of
The masonry entry is direct about this: older buildings rarely carry a record of what was altered and when, so establishing what is carrying, what has already been removed and what is currently propping what is a survey exercise, and assumptions made from appearance are unreliable.
The same is true beneath the ground. What the existing foundation is, what it bears on and what it is carrying are established by investigation rather than assumed, which is why the first item in an extension foundation discussion is usually a trial hole rather than a drawing.
Matching depth is not matching a number
Founding level is chosen for the stratum and the influences around it. Matching the existing foundation therefore means understanding what it is founded on, not measuring how deep it happens to be, because two excavations to the same depth can arrive at very different formations.
Where the new work has to go deeper, for trees, for a different stratum or because the existing is shallow, the new foundation is founding lower than its neighbour. That is a step in the foundation line, and the wall above spans a transition between two different bearing conditions.
Old and new settle differently, because one has already settled
New construction applies a load the ground has not carried before, and the ground responds. The existing building applied its load a long time ago. Even where both are founded identically, the two halves of the finished house are at different points in the same process.
Differential movement between elements founded differently is the characteristic risk the library keeps naming, and it is what the junction detail exists to deal with rather than to conceal.
Tied, or deliberately separated
Two approaches exist and they are opposites. Tying the structures together makes them act as one and relies on the connection being able to do that; separating them accepts that they will move differently and provides a joint where the movement can occur.
The masonry entry is useful on why this is not a detail to improvise. Ties between new and existing masonry are what make separate elements act together, and where they are missing, elements that look joined behave as if they are not. A movement joint bridged by a tie or a bonded return is not a joint at all.
- What the connection, if any, is being asked to transfer
- Where the joint is intended to fall, and whether anything bridges it
- How the damp control passes through or across the junction
- How the same junction is finished so movement is not hidden by rendering over it
The existing wall gains a new job
An extension usually opens the wall it joins. That wall is carrying floors and roof and is also being held in line by the floors and returning walls that meet it, and an opening interrupts both duties at once. Widening an opening lengthens what is being carried and shortens what is carrying it in the same operation.
Whether the existing foundation is being asked to carry a different load or the same load differently distributed is the question the entry puts to professionals, and beam-end reactions arriving at a pier are a concentration where a distributed load used to be.
Excavating beside what is already standing
Digging the new foundation means taking ground away next to the old one. The strip entry names later trenching alongside a strip as removing support the strip was relying on, and the drainage entry repeats it: a trench beside a foundation removes support, and a foundation bearing over a drain imposes load a drain cannot take.
That makes sequence part of the design rather than a contractor's choice, and it is why temporary support may be required before anything is opened.
The buried layers have to be rejoined
The new floor's membrane, the new wall's damp-proof course and whatever exists in the old building all have to become one line at the junction. Where the existing course sits relative to the new internal floor and the new external ground level is set by the old building rather than by the new drawing, and that constraint is easier to meet before anything is cast.
Extension foundation junction checklist
- 1Ask for a trial hole to establish what the existing foundation is and what it bears on.
- 2Ask what ground investigation supports the new foundation design.
- 3Establish whether the new work founds at the same level as the existing, and why.
- 4Ask what happens where the new founding level meets the old one.
- 5Establish whether the structures are to be tied or deliberately separated.
- 6If separated, ask where the joint falls and confirm nothing bridges it.
- 7Ask whether the existing foundation is being asked to carry a different load.
- 8Ask where beam reactions from any new opening reach the ground.
- 9Ask what temporary support the excavation and the opening require, and who designs it.
- 10Establish how the new floor membrane joins the existing damp control.
- 11Ask where drains run relative to both foundations, and what protects them.
- 12Record what was found in the trial hole; it is the only account of the old foundation.
Common mistakes to avoid
- Matching the existing foundation by depth when what matters is the stratum it was founded on.
- Assuming the existing foundation is what it looks like, when older buildings rarely carry a record of earlier alteration.
- Expecting old and new to settle identically, when one has been carrying a load for decades and the other has not.
- Drawing a movement joint and then tying or bonding across it, which stops it being a joint.
- Treating the opening into the existing wall as separate from the foundation discussion, when the beam reactions have to reach the ground.
- Digging the new trench beside the old footing without asking what support is being removed.
- Leaving the junction of the new floor membrane and the existing damp control until after the slab is cast.
When to involve a professional
- Whether two structures should be tied or separated, and at what level new work should found, are structural determinations for a qualified engineer at that building.
- What an existing foundation is and what it bears on is established by investigation, not inferred from the age or appearance of the building.
- Forming or widening an opening in an existing wall is a whole-structure question, including the temporary support required and when it may be removed.
- Where work approaches a shared boundary or a neighbour's structure, obligations apply that vary by jurisdiction and are checked locally before work is planned.
- Nothing here states a founding level, a joint arrangement, a tie specification or any dimension.
Frequently asked questions
Questions readers ask about this topic
Should a new extension foundation match the old one exactly?
Matching means founding on the same conditions rather than at the same depth, because two excavations to the same depth can reach very different formations. Whether that is achievable and appropriate at a given building is a determination for the engineer designing it.
Is it better to tie the extension to the house or separate it?
They are different strategies, not a better and a worse one. Tying relies on the connection making the two act as one; separating accepts they will move differently and provides a joint for it. Which applies is a structural decision for that building.
Why has a crack appeared where my extension meets the house?
Differential movement between parts founded differently is the risk the reference entries keep naming, but a crack at a junction is evidence to be assessed rather than a diagnosis. Movement in a building is reviewed by a qualified engineer before any remedy is designed.
Do I need to dig a trial hole before designing?
An engineer usually wants to know what the existing foundation is and what it bears on, and that is established by investigation rather than assumption. What form that takes at a particular building is part of the brief you agree at the outset.
Can the new trench be dug right up to the old footing?
Taking ground away beside an existing foundation removes support it was relying on, which is why the reference entries name later trenching alongside a strip as a hazard. Sequence and any temporary support are part of the design rather than a site decision.