Skip to main content
HELPERG Ecosystem
Build Design HubBuild Design Hub

Construction · Failure Mode · Floors

Why Concrete Floor Slabs Crack and Move

Published

Four entries in the reference library end with a version of the same design question: where are movement and construction joints intended to fall. None of them answers it, because a joint layout belongs to the designer of a particular floor and an encyclopedia entry cannot see one.

What can be explained is the mechanism behind the question. A slab shrinks as it cures and moves with temperature afterwards, and where joints are placed, and whether the perimeter lets the slab move at all, determines whether that movement is taken up in planned lines or expressed as random cracking through the finish.

This guide separates the joints that look alike and do opposite things. It states no spacing, no width and no allowance, because joint provision is a design calculation based on the materials, geometry and exposure of a specific construction.

Who this guide is for

  • Owners who have found a crack in a new concrete floor and want to understand what it is
  • Self-builders reading a slab drawing with joint lines on it
  • Anyone choosing a rigid floor covering over a concrete base
  • Owners planning a polished or exposed concrete floor
  • Anyone about to lay a finish across a line already in the construction

A slab is not finished when it is cast

Concrete placed today is a different element next month. It shrinks as it cures, giving up the water it was mixed with, and afterwards it goes on responding to temperature. Those are not defects; they are what the material does, and a floor is designed around them rather than in spite of them.

The question a design answers is therefore not whether the slab will move but where the consequence of that movement will appear.

Restraint is what turns movement into cracking

A slab free to shorten shortens. A slab held still while it tries to shorten builds up force against whatever is holding it, and the material resolves that force by cracking somewhere it chose for itself. That is why the perimeter condition matters as much as the joint layout: the compressible strip at the edge exists so the slab can move without bearing hard against the surrounding structure.

The post-tensioned slab entry states the same principle in its most extreme form, where the freedom to shorten is the mechanism rather than a tolerance, and anything that holds the plate still takes part of the force that was intended for the concrete.

Bonded and unbonded layers fail in opposite directions

A layer laid over a deck either acts with it or independently of it, and that single decision follows from what the layer is for. The library states the consequences in both directions: a bonded topping cracks if the deck moves, and an unbonded one curls as it shrinks. Neither is a defect in itself — each is what that arrangement does — and the failure is in choosing the wrong one for the purpose.

This is why a crack in a floor is rarely diagnosable from the crack alone. What the layer was arranged to do has to be established first.

Which joint is doing which job

Two lines in a concrete floor can look identical and mean opposite things. A construction joint is the plane where one pour was stopped and the next cast against it, and the finished element is meant to behave as though the joint were not there. A movement joint is a deliberate discontinuity provided so parts of a construction can move relative to each other.

The library gives a physical tell rather than an appearance test. A construction joint is normally crossed by continuous reinforcement, because it is meant to act as one member; a movement joint is deliberately free of anything restraining the movement it exists to permit. It also notes that the sawn or formed contraction joint in a slab is a movement joint under a third name, and not a pour break.

  • Construction joint: where work stopped and restarted, intended to act as continuous
  • Movement joint: a designed discontinuity, intended to move
  • Contraction joint: a movement joint under another name, controlling where shrinkage cracks form
  • A crack: where movement occurred without provision having been made for it

A joint carried through, or a joint eliminated

A movement joint only works if it passes through everything that has to move, including whatever is applied over it. A rigid finish laid across a movement joint has eliminated it. The movement still occurs, and the crack appears in the finish, usually a short distance from where the joint was, and usually in a position nobody would have chosen.

The same applies upward through a build-up. Where a joint in the structure has to be carried up through an isolated layer above, and where that layer may run over, is decided from the structural layout rather than from the screed layout.

Positions follow the movement, not the room layout

Joint positions are determined by where movement concentrates, which follows from the materials and the geometry rather than from convenience. That is why the design question in the entries pairs joints with the room layout: not because the layout decides the joints, but because the two have to be reconciled before a covering is chosen.

Joint positions are also where the programme and the design negotiate. A pour break that suits the plant and the working day may not be a break the designer has allowed, and the resolution belongs to the designer.

Why the entity pages ask and do not answer

A joint layout is a design output for one floor, calculated against its materials, geometry and exposure. No entry describing a construction in general can supply it, which is why four of them raise it as a question to take to a professional and stop there. The useful move for a reader is to ask the question early enough that the answer can still shape the finish.

Joints and movement in a concrete floor

  1. 1Ask where movement and construction joints are intended to fall in this floor.
  2. 2Ask who determined those positions and against what.
  3. 3Establish which lines are intended to move and which are intended to act as continuous.
  4. 4Ask what reinforcement crosses each construction joint.
  5. 5Confirm how the slab is isolated from the surrounding structure at its perimeter.
  6. 6Ask what is expected to happen as the slab shrinks, and over what kind of period.
  7. 7Check whether the intended covering layout agrees with the joint positions.
  8. 8Ask how each movement joint is carried through the finish rather than covered by it.
  9. 9Where a build-up sits over the slab, ask which structural joints have to continue upward.
  10. 10Ask whether any layer is bonded or deliberately separated, and which was intended.
  11. 11Photograph the joint layout before it is covered, and keep it with the building record.
  12. 12If a crack appears, record where it runs relative to the joints before anyone fills it.

Common mistakes to avoid

  • Reading every line in a concrete floor as the same kind of joint, when two of them have opposite intentions.
  • Laying a rigid finish across a movement joint, which eliminates it and relocates the crack into the finish.
  • Treating a visible line on a finished surface as proof of a movement joint, when a construction joint can show too.
  • Assuming a pour break can be placed wherever the working day ends, when the position is a design decision.
  • Expecting a slab held hard against the surrounding structure to shrink without consequence.
  • Substituting a levelling screed for a structural topping, which looks like a finishes decision and is not.
  • Choosing a floor covering layout before the joint positions in the base are known.

When to involve a professional

  • Joint provision is a design calculation based on the materials, geometry and exposure of a specific construction, and nothing here states a spacing or a width.
  • Where a construction joint may be placed in a particular structure, and what it must carry, is determined by the designer of that structure.
  • Slab thickness, reinforcement and joint layout are structural decisions for a qualified engineer.
  • Diagnosing a crack in an existing floor requires investigation of the whole construction rather than inspection of the crack alone.

Frequently asked questions

Questions readers ask about this topic

Is a crack in a new concrete floor always a defect?

Not necessarily, and the reference entries deliberately avoid saying. What they do explain is that concrete shrinks as it cures and moves afterwards, and that whether the consequence appears in planned lines or as random cracking depends on the joints and the restraint around the slab.

What is the difference between a construction joint and a movement joint?

Intention. A construction joint is where one pour stopped and the next was cast against it, and the element is meant to behave as though it were not there. A movement joint is a deliberate discontinuity provided so parts can move relative to each other.

How can I tell which joint I am looking at?

Not by appearance. The library gives the reinforcement as the physical tell: a construction joint is normally crossed by continuous reinforcement because it is meant to act as one member, while a movement joint is deliberately free of anything restraining the movement it permits.

Can a tiled floor be laid straight over a joint?

A rigid finish laid across a movement joint has eliminated it. The movement still occurs and the crack appears in the finish, usually a short distance from where the joint was. How a joint is carried through a covering is settled with the covering rather than after it.

Why does nobody give a joint spacing?

Because joint positions follow from where movement concentrates, which depends on the materials, the geometry and the exposure of a particular floor. A figure quoted without those inputs would be a determination about a building nobody making it has seen.

Keep reading

Related guides and sections