Checklists · Construction planning
Construction Tender Package Preparation Checklist
To help an owner assemble a consistent, complete information pack for a construction project so that everyone responding is answering the same question and the differences between responses are visible.
8 sections · 40 planning prompts · educational owner-side preparation
https://www.builddesignhub.com/checklists/construction-project-planning/construction-tender-package-preparation · Build Design Hub — educational planning resource. Requirements vary by project and location.
Scope
What this checklist covers
The preparation ground these prompts walk through.
- Stating plainly what is being asked for and what sits outside the package
- Assembling drawings and information with revisions that agree with each other
- Describing inclusions, exclusions and what you are supplying yourself
- Site conditions and constraints the pack has to describe honestly
- Handling the items that are genuinely still undecided
- Keeping questions and answers visible to everyone who received the pack
Audience
Who this checklist is for
- Owners assembling information for a construction project with professional support
- Self-builders preparing to approach contractors with a defined package of work
- Owners who have had responses that turned out not to be comparable
- Anyone coordinating separate packages of work on the same project
Timing
When to use it
- Checking that an information pack is internally consistent before it is issued
- Writing down what you assume is included so it can be confirmed rather than assumed
- Describing site constraints honestly rather than leaving them to be discovered
- Preparing the process questions to put to your professional adviser
- Understanding why apparently similar responses turn out to describe different work
Limits
When it is not sufficient
This is general planning preparation. These situations need a qualified professional, and often the relevant authority.
- Deciding what form of agreement to use, which is a legal matter for a suitably qualified adviser
- Establishing what any response should contain or how it should be evaluated commercially
- Determining what consents, permissions or requirements apply, which have to be confirmed locally
- Replacing a specification, schedule of works or drawing prepared by a qualified professional
- Assessing whether anyone responding is suitable for the work, which is not something this material can do
The checklist
Work through the sections
Tick the boxes on paper or on screen — nothing is stored, so print the page if you want to keep your marks.
1.Saying plainly what is being asked for
Packages fail most often because the question inside them was never stated in words anybody could read quickly.
Write a short plain description of what you want built, as if explaining it to someone who has not seen the drawings, then check whether the pack actually says that.
If your own summary and the pack disagree, the pack is unclear, and it is far easier to fix that now than to explain it afterwards.
Decide and record which parts of the work sit inside this package and which you intend to arrange separately, and say so explicitly in the pack.
Work arranged separately has to be visible to everyone, because it affects sequence, access and responsibility on site.
Note whether you are asking for the work as drawn, or inviting alternative approaches to be described, since those are different questions.
Mixing the two produces responses that cannot be laid side by side, which is the most common source of confusion.
Record who is coordinating the package and who everyone responding should contact, and make sure only that route is used.
Multiple contact routes result in different people being told different things, which is exactly what a package is meant to prevent.
Ask what form of agreement is anticipated for this work and confirm the position with a suitably qualified adviser before the pack goes out.
The intended arrangement affects what the pack has to contain, so it belongs at the start rather than at the end.
The form of any agreement is a legal matter and must be settled with a suitably qualified adviser, not decided from a checklist.
2.Assembling the drawings and information
The most common defect in a pack is not a missing drawing but two drawings that contradict each other.
List every drawing, schedule and note you intend to issue with its revision marking, then check the folder actually contains what the list says.
The document list is what everyone will refer back to, and it is worth checking against reality before it is issued.
Take superseded drawings out of the pack rather than leaving them in as background, and say plainly what has been withdrawn.
An old revision left in a pack will be worked from by somebody, and the disagreement surfaces at the worst possible moment.
Check that each drawing carries a revision reference and that the reference on the sheet matches the one on your list.
Mismatched revision markings are easy to spot before issue and very hard to unpick once several people hold different sheets.
Mark which documents are for information only and which describe the work to be carried out, so nobody has to guess the status of a survey or a report.
Reports issued for context are frequently read as instructions, and a single line of labelling prevents it.
Ask whether a specification or schedule of works exists, who is producing it, and whether it is being issued with the drawings.
Drawings show arrangement rather than quality, and the written material is where most of the difference between responses lives.
A specification is a professional document; ask your design team who is producing it rather than attempting to write one yourself.
3.Inclusions, exclusions and what you are supplying
Every awkward conversation later begins as something that was assumed to be included by one side and not the other.
Write down the things you are assuming are included, and ask that each response states clearly whether they are.
Assumptions written down become questions that can be answered; assumptions left in your head become disputes.
List what you intend to supply yourself — appliances, sanitaryware, lighting, ironmongery — and say for each one who is expected to fit it.
Owner-supplied items are a well-known source of confusion about responsibility, delivery and what happens if something arrives damaged.
Record what is to happen to everything removed, including anything you want kept, salvaged or reused.
Items an owner intended to keep are routinely skipped because nobody wrote them down before the strip-out began.
Note what site facilities you are providing and what you expect to be provided, including power, water and welfare arrangements.
These arrangements differ between projects and are usually assumed rather than stated, which is how they end up unresolved on the first morning.
Ask that anything excluded is listed explicitly in the response rather than simply left unmentioned.
Silence is not an exclusion or an inclusion, and asking for the list is the only reliable way to find out which it was.
4.Describing the site as it really is
A pack that oversells the site produces responses that have to be revisited. Describing constraints plainly serves everybody, including you.
Describe the access route as it actually is, including anything that restricts a vehicle, and invite anyone responding to see it for themselves.
Access is the constraint most often discovered on arrival, and it affects how nearly every part of the work is carried out.
Mark on a plan where materials could be stored and where they could not, including areas you need to keep clear.
Storage is negotiated on the first morning unless it has been described, and by then the options are whatever is left.
Record any restriction you already know about on working hours, noise, parking or deliveries, and confirm locally what applies.
Restrictions vary by location and by property, and they are far better raised in the pack than discovered afterwards.
Restrictions on working hours, parking and similar matters have to be confirmed with the relevant authority and any managing party.
State which parts of the property remain occupied or in use during the work, and what that means for access and separation.
Working around occupation changes how work is planned, and it must be in the pack rather than mentioned in conversation.
Record what is known about the ground, the existing structure and the services, labelling each item as documented, observed or unknown.
Honest labelling protects you, because a confident statement that turns out to be wrong is worse than an admitted uncertainty.
Anything stated about ground conditions or existing structure should come from qualified professionals and be issued as their document.
5.The items that are genuinely still undecided
Every package has them. The problem is never their existence; it is pretending they do not exist.
List every item that is genuinely undecided and say so in the pack, rather than leaving a blank that will be filled in by assumption.
A stated unknown can be handled; a silent one produces responses that differ for reasons nobody can see.
Ask by which stage of the work each outstanding decision would be needed, and record the answer against each item.
This turns an intimidating list into an ordered one and shows you which choices genuinely cannot wait.
Ask how items that are not yet chosen should be dealt with in a response, and make sure everyone is told the same thing.
If each responder handles the unknowns differently, the responses stop being comparable regardless of how good they are.
Record which choices you would be willing to leave to someone else within a described standard, and which you want to make yourself.
Being explicit about this reduces the number of items that have to be resolved before anything can move.
Note the items where a late change would disturb the most other work, and concentrate your attention on deciding those first.
Not all late decisions are equally disruptive, and knowing which are worst is a question the design team can answer.
Which decisions constrain others is a professional judgement; ask the design team rather than ranking them yourself.
6.Making responses answer the same question
Comparability is created before the pack goes out, not afterwards when responses are spread across a table.
Make sure everyone responding receives the same pack at the same revision, and record which issue each recipient was sent.
Different recipients holding different revisions is the most common reason responses cannot be compared at all.
Ask that responses follow the same structure, so that what each one includes can be seen without decoding it.
A common structure is a modest request that makes an enormous difference when several responses arrive.
Where a response describes something different from the drawings, record it as a difference to be discussed rather than assuming it is a mistake.
Differences often reveal a genuine problem with the pack, and treating them as errors loses that information.
Note every assumption a response states, since assumptions are where apparently identical submissions actually differ.
Two responses can describe the same work and mean very different things once their assumptions are read.
Ask a qualified professional to go through the responses with you, particularly where the package is substantial or technical.
Reading responses is a skill, and the differences that matter are often not the ones an owner notices first.
Evaluating responses is professional work; nothing in this checklist indicates whether any response or party is suitable.
7.Questions during the process and how answers travel
Answering one person privately quietly destroys the comparability you spent the whole pack building.
Agree in writing how questions are to be asked during the process and who answers them, and state that route in the pack.
Without a stated route, questions arrive through whichever contact somebody happens to have.
Record every question asked and issue the answer to everyone who received the pack, whether or not they asked it.
This is the mechanism that keeps responses comparable, and it also gives everyone the benefit of the sharpest question.
Where a question reveals a gap in the pack, issue a correction to everyone rather than answering it privately.
A gap answered privately becomes an invisible difference between the responses that arrive.
Keep a numbered log of clarifications issued, so it is possible to establish later what was known and when.
This log becomes the record of what everyone was working from, and it is difficult to reconstruct afterwards.
Ask what happens if a drawing has to be revised while responses are being prepared, and agree that in advance.
Mid-process revisions do happen, and having agreed how they are handled avoids improvising under pressure.
How a revision issued mid-process should be handled is a matter for your professional adviser to guide.
8.Reading the responses that come back
The useful information in a set of responses is usually in the parts owners read last.
Read the exclusions and stated assumptions in each response before anything else, since that is where responses differ most.
What has been left out shapes everything else, and reading it first changes how the rest is understood.
Note which responses answered the question you asked and which answered a slightly different one.
A response describing different work is not necessarily worse, but it must be recognised as a different proposition.
Ask any responder to explain in writing what a particular item covers rather than assuming you have understood it correctly.
Written clarification is quick to obtain at this stage and becomes part of the record of what was agreed.
Write down the reasons for your decision at the time you make it, in your own words, and keep it with the responses.
Reasoning fades quickly, and a contemporaneous note is useful both to you and to anyone advising you later.
Agree in writing exactly which documents form part of the arrangement that follows, including any clarifications issued.
Ambiguity about which documents apply is one of the hardest things to unpick once work is under way.
What forms an agreement and how it is executed are legal matters for a suitably qualified adviser.
Preparation
Documents and information to gather
Having these to hand usually makes the first conversation shorter and more useful.
- The full list of drawings and documents you intend to issue, each with its revision marking
- Any survey, report or investigation you hold, marked clearly as information rather than instruction
- Your written plain-words description of what is being asked for
- A marked plan showing access, storage areas and any part of the property remaining in use
- The list of items you intend to supply yourself, with a note of who fits each one
- Notes of any restriction you already know about affecting hours, parking or deliveries
- The record of which recipient was sent which issue of the pack
Records
Decisions to record before work begins
Write these down in your own words, with the date, so everyone is working from the same version.
- Which parts of the work are inside this package and which you are arranging separately
- Whether you are asking for the work as drawn or inviting alternative approaches
- What you are supplying yourself and who is expected to fit each item
- What is to happen to everything removed, including anything you want salvaged
- Which items are genuinely undecided and how you have asked them to be handled
- Which choices you are willing to delegate within a described standard
- Which documents you intend to form part of the arrangement that follows
Professional review
Questions to discuss with qualified professionals
Bring these to the relevant qualified professional, supplier or authority. Requirements vary by project and location.
- Is this pack internally consistent, and does anything in it contradict anything else?
- Who is producing the specification or schedule of works, and is it being issued with the drawings?
- What form of agreement is anticipated, and what does the pack need to contain because of it?
- How should the items that are still undecided be dealt with in the responses?
- Which of my outstanding decisions constrain the most other work?
- How should questions during the process be handled so that everyone receives the same answers?
- What should I be reading for first when the responses arrive?
- What happens if a drawing has to be revised while responses are being prepared?
Blind spots
Commonly overlooked items
- Superseded drawings left in the pack as background, which somebody will work from
- Items the owner intends to keep or salvage, which are removed because nobody wrote them down
- Who fits owner-supplied items and what happens if one arrives damaged
- Site facilities such as power, water and welfare, which are assumed rather than stated
- Answers given privately to one question, which quietly make responses incomparable
- Labelling reports as information only, without which they are read as instructions
- Recording which recipient received which issue of the pack
What this checklist does not do
- This checklist helps you organise information; it does not tell you how work should be procured, what any response should contain, or whether anyone responding is suitable for the work.
- Anything the pack says about ground, structure or services should originate from qualified professionals and be issued as their document rather than as your summary.
- Consents, permissions and restrictions on how work may be carried out have to be confirmed with the relevant authority, and a pack cannot establish them.
- The form of any agreement, and which documents form part of it, are legal matters for a suitably qualified adviser.
More preparation
Related checklists
Inspiration
Related Ideas Library pages
Design directions to explore once the preparation is done.
Go deeper
Related Build Design Hub guides
Explanatory planning guidance behind the decisions on this page.
Construction Project Planning Checklists
Owner-side preparation checklists for new-build and major construction projects — scope, information to gather and the questions to bring to qualified professionals.
Browse all Construction Planning checklists →