Design Responsibility Map Preparation Checklist
Helps an owner build a single record of design authorship element by element, including the junctions between packages, so that parts of the project nobody has been appointed to design are found early.
7 sections · 38 planning prompts · educational owner-side preparation
https://www.builddesignhub.com/checklists/project-documentation-and-changes/design-responsibility-map-preparation · Build Design Hub — educational planning resource. Requirements vary by project and location.
Scope
What this checklist covers
The preparation ground these prompts walk through.
- Why design authorship is a separate list from who builds each element
- Walking the building and listing the elements to be attributed
- Elements commonly designed by a specialist rather than the lead designer
- The junctions between two packages, where each side's scope stops
- Who checks, who coordinates and whether anybody has that task
- Keeping the map current as the design and the team change
Audience
Who this checklist is for
- Owners assembling a project team and unsure who covers what
- Households told that part of their project will be designed by a supplier
- Owners who have had a question referred back and forth between two parties
- Anyone who wants one page showing who is responsible for designing what
Timing
When to use it
- Owners preparing questions before appointing the last members of a project team
- Households who want the gaps between appointments visible before work starts
- Owners whose project includes elements designed by whoever supplies them
- Anyone preparing for a pre-start conversation about who designs the junctions
- Reviewing an existing team to see whether any subject is uncovered
Limits
When it is not sufficient
This is general planning preparation. These situations need a qualified professional, and often the relevant authority.
- Deciding what design input your project requires, which is a matter for a suitably qualified professional
- Allocating design responsibility between parties, which is done through their appointments and not by an owner's notes
- Judging whether any design is adequate, which needs independent professional review
- Establishing legal responsibility for a design, which is a question for your own legal adviser
The checklist
Work through the sections
Tick the boxes on paper or on screen — nothing is stored, so print the page if you want to keep your marks.
2.Listing the elements to be attributed
Work outwards from the ground. The list does not need technical accuracy; it needs to cover everything, in words you can use in a conversation.
Start below ground with anything in contact with the earth, including what the building sits on and anything retaining a change of level.
Below-ground elements are the ones most likely to involve a specialist the owner has never heard of.
List the structure next, separating the members from the connections between them, since those are frequently designed by different parties.
The library is consistent that a member and the way it is attached are routinely separate design questions.
List the outside of the building as separate items, including the walls, the roof, the openings and anything that keeps water out.
Water exclusion is often a designed system in its own right rather than a property of the wall or roof it sits in.
List the services as items, noting where they pass through a structure, since a route through a structural element is a design output.
A service route through a floor is settled between the structural designer and whoever is running the services, before work starts.
List fitted interior elements, including anything hung from or fixed to a structure, since the fixing may be somebody else's design.
Fixing something to a lining or a decoupled element is a recognised question about the connection rather than about the board.
List everything outside the building as separate items, including surfaces, retaining elements, drainage, boundary structures and anything that has to carry a vehicle.
External works are the part of a project most likely to proceed without anyone having designed it at all.
3.Elements normally designed by a specialist
This is the section most likely to surface something nobody has arranged. Ask about each of these by name rather than in general terms.
Ask who designs any engineered component supplied to the project, and whether that design happens before or after it is ordered.
Some components are designed as part of manufacture, which puts their design deadline before the order rather than after.
Ask specifically who designs the connections between structural members, as distinct from whoever sized the members that the connections join together.
Connections are a classic separately designed item, and an owner would have no reason to suspect the split exists.
Ask who is designing any arrangement that keeps water out of a below-ground or buried space, and whether that is a distinct appointment.
Below-ground water exclusion is described in the published material as a specialist design discipline depending on surveyed site conditions.
Below-ground waterproofing design depends on the conditions surveyed on your site; ask who is doing it rather than assuming it is included.
Ask who is designing the temporary arrangements needed while the building is being built, who may change them, and what becomes permanent.
Temporary works are a design subject in their own right, and the library notes that some temporary elements are left in place by default rather than by decision.
Ask who designs any proprietary system supplied as a package, and whether their design covers how it meets the surrounding construction.
A supplier's design usually stops at the edge of their own product, which is exactly where the junction begins.
Ask whether any part of the project is governed by a separate design carried out by somebody else, and how that reaches the rest of the team.
The published material notes that requirements determined by a separately carried out design can take precedence over other records of the same element.
4.The junctions between packages
This is the finding the whole map exists to act on: each side's scope stops at the junction, so the junction belongs to nobody unless somebody claims it.
For each pair of adjoining elements on your list, write down the junction between them as an item in its own right.
Writing a junction as an item is what makes it possible to ask who owns it; otherwise it is invisible.
Ask, for each junction, who is designing the junction itself rather than the two things it joins, and record the answer or its absence.
An absent answer is the most valuable output of this exercise and should be recorded as plainly as a positive one.
Pay particular attention to junctions where something has to continue from one element into the next rather than simply meet it.
The published records describe continuity at a corner as the part most often left out of both packages because neither trade regards it as theirs.
Ask who designs and supplies anything that closes a gap at a junction, since these items sit precisely between two scopes.
Closure items are the physical form the gap takes, and they are omitted for the same reason the design is.
Ask whether any drawing of the junction exists, and if not, whether one is expected before work reaches that point.
A junction with no drawing is usually resolved by whoever is holding a tool, which is a design decision made without information.
A junction resolved on site without a drawing is a design decision made by somebody who may not have the information; raise it rather than leaving it.
Keep a short list of junctions nobody has claimed and bring it to every design conversation until each one has a name against it.
Persistence is what closes these, because each conversation tends to address only the junction in front of it.
5.Who checks and who coordinates
Designing, checking and coordinating are three tasks. A project can have all the design covered and none of the coordination.
Ask who reads a specialist's design when it arrives, against what they read it, and whether reviewing it is part of anybody's appointment.
Specialist design frequently arrives and is filed, with nobody appointed to read it against the rest of the project.
Ask what reviewing means in that person's appointment, since the word carries a narrower meaning professionally than in ordinary use.
Owners hear review as checking and professionals mean something more limited, which is worth clarifying once.
Ask who holds the whole set of design information, including the parts produced by specialists, and whether anybody has all of it.
A project where no single party holds the whole set is one where interactions between packages cannot be seen.
Ask who is coordinating between the designers, and whether that role appears in any appointment or has fallen to you by default.
Coordination is a task, and if it appears in no appointment the owner is usually performing it without having agreed to.
If coordination between designers appears to sit with you, say so plainly to each party and take advice on whether that arrangement is workable.
Ask how a specialist's design reaches the other parties who need it, and whether that route exists or is assumed.
Information that reaches only the party who commissioned it is the ordinary mechanism by which a junction goes unnoticed.
6.What the map cannot settle
The map is a record of what you have been told. Being clear about its limits keeps it useful rather than dangerous.
Note on the map itself that it records what you were told and does not appoint anybody to anything.
A document that looks like an allocation will be read as one by somebody who was not part of the conversation.
Record who told you each attribution and when, so a later disagreement starts from a conversation rather than from your summary.
Attributions change as a team develops, and the source is what makes an out-of-date entry recognisable.
Send the map to each party and ask them to confirm or correct the lines attributed to them, rather than filing it unchecked.
Confirmation converts your understanding into theirs, which is the only version that matters on site.
Where a gap appears, raise it rather than deciding who ought to cover it, since allocating design work is not an owner's decision.
An owner assigning design work informally creates exactly the ambiguity the map was written to remove.
Keep any question about responsibility or liability separate from the map and take it to your own legal adviser.
Mixing the two makes the practical document harder to use and the legal question harder to answer.
7.Keeping the map current
The map goes out of date at every appointment, every change and every substitution. Small maintenance keeps it honest.
Update the map whenever somebody new is appointed, and ask the new party which lines they now hold and which they do not.
A new appointment rarely covers exactly what everybody assumed it would.
Check the map when a product is substituted, since a different product can carry a different design arrangement with it.
A substitution can move an element from designed-by-the-supplier to designed-by-nobody without anyone noticing.
When the design changes, look for junctions that did not exist before, and add them to the unowned list until somebody claims them.
New junctions created by a change are the least likely to have an owner, because the original allocation predates them.
Read the map through before work begins and again before each package starts, focusing on the lines with nothing written against them.
The moment before a package starts is the last cheap opportunity to find its gaps.
Keep the map with the project papers at completion, since it records who designed what for whoever needs to know later.
Knowing who designed an element is useful years later, when somebody wants to alter it.
Preparation
Documents and information to gather
Having these to hand usually makes the first conversation shorter and more useful.
- Appointment documents or proposals for every party engaged on the project
- The drawing set, with a note of which parties produced which sheets
- Any specification or schedule describing elements to be designed by a supplier
- Correspondence in which somebody described an element as belonging to another party
- Any specialist design already received, and a note of who has read it
- A list of the packages the works are divided into, if one exists
Records
Decisions to record before work begins
Write these down in your own words, with the date, so everyone is working from the same version.
- Who is designing each element on your list, and who told you so
- Which elements are designed by whoever supplies them, and when that design happens
- Which junctions have a named designer and which currently have nobody
- Who reads specialist design when it arrives, and what reviewing means in their appointment
- Who is coordinating between designers, and whether that appears in any appointment
- Where the map is kept, who has confirmed their lines on it, and when it was last updated
Professional review
Questions to discuss with qualified professionals
Bring these to the relevant qualified professional, supplier or authority. Requirements vary by project and location.
- Ask which elements of this project they are designing and which they expect somebody else to design
- Ask who designs the connections between structural members
- Ask who is designing any arrangement that keeps water out of a buried or below-ground space
- Ask who is designing the temporary arrangements and whether anything temporary is intended to remain
- Ask whether a supplier's design covers how their product meets the surrounding construction
- Ask who is designing each junction between two packages
- Ask who reads specialist design when it arrives and against what
- Ask who is coordinating between the designers on this project
- Ask whether any part of this project is currently outside everybody's appointment
Blind spots
Commonly overlooked items
- Connections between structural members, frequently designed separately from the members
- How a supplier's designed package meets the construction around it
- Temporary arrangements during construction, and which of them are intended to remain
- Closure pieces at a junction, which sit precisely between two scopes
- Whether anybody is appointed to read specialist design when it arrives
- Junctions created by a later change, which predate nobody's allocation
- External works, which frequently proceed without anybody having designed them
What this checklist does not do
- This map records what you were told; it appoints nobody, allocates nothing and cannot move responsibility from one party to another
- What design input a project requires is a matter for a suitably qualified professional, not something an owner should conclude from a list
- Where a gap appears, raise it with the appointed professionals rather than deciding who ought to cover it
- Questions about legal responsibility for a design belong with your own legal adviser and should be kept separate from this record
More preparation
Related checklists
Inspiration
Related Ideas Library pages
Design directions to explore once the preparation is done.
Go deeper
Related Build Design Hub guides
Explanatory planning guidance behind the decisions on this page.