Checklists · Documentation
Scope of Works Document Review Checklist
Helps an owner examine a scope of works line by line, testing where the work starts and stops, which handovers between trades are unassigned and what the document assumes about the existing building.
7 sections · 42 planning prompts · educational owner-side preparation
https://www.builddesignhub.com/checklists/project-documentation-and-changes/scope-of-works-document-review · Build Design Hub — educational planning resource. Requirements vary by project and location.
Scope
What this checklist covers
The preparation ground these prompts walk through.
- Establishing what the scope document is based on and which drawings it follows
- Testing where the work stops at the edge of each room, storey and external area
- Finding the handovers between trades that no line of the scope claims
- Reading the assumptions the scope makes about the existing building
- Access, protection and occupation arrangements described or left out
- Clearing away, making good and the condition the property is handed back in
Audience
Who this checklist is for
- Owners sent a scope of works and unsure how far the described work reaches
- People comparing scope documents from different builders that describe the work differently
- Owners planning to live in part of the property while the work is under way
- Anyone who has had work stop at an edge nobody had thought to write down
Timing
When to use it
- Reading a scope document closely before any conversation about accepting it
- Listing the boundaries where the work stops and asking what happens beyond them
- Identifying work between trades that no line of the document appears to cover
- Preparing questions about access, protection and use of the property during the work
- Recording what the scope assumes about the existing building before anything is opened up
Limits
When it is not sufficient
This is general planning preparation. These situations need a qualified professional, and often the relevant authority.
- Judging whether a scope of works is complete or adequate for your project
- Deciding what work is technically necessary, which belongs with qualified professionals
- Interpreting the contractual effect of scope wording, which belongs with your own legal adviser
- Telling you what any authority requires for the work described here, which has to be raised locally
- Comparing one contractor document against another on anything other than what each describes
The checklist
Work through the sections
Tick the boxes on paper or on screen — nothing is stored, so print the page if you want to keep your marks.
1.What the scope document rests on
A scope of works is always written against something. Finding out what that something is tells you how much of it was assumed rather than examined.
Ask which drawings and which issue of them the scope was written against, and note whether you hold that same issue yourself.
A scope written against an earlier layout describes a job that no longer exists, and nothing on the face of the document reveals it.
Ask whether the person who wrote the scope has been to the property, which rooms they saw and whether anything was inaccessible when they were there.
Scope written from drawings alone tends to omit exactly the awkward corners an owner already knows are difficult.
Note where wording repeats between rooms word for word, and ask whether those sections were written for your property or carried over from a template.
Repeated wording is not necessarily wrong, but it is a good indication of where nobody has looked closely at your particular situation.
Read your own written brief alongside the scope and mark anything you asked for that does not appear anywhere in the document.
Items dropped between the brief and the scope are rarely dropped deliberately; they simply never got written down again.
Ask what is meant to happen to the scope when a drawing is revised, and who is responsible for updating the document to match.
How a scope tracks a drawing revision depends on the arrangement in place; ask the appointed professionals rather than assuming it updates itself.
Record the date and any issue marking on the scope document, and keep every earlier version you were sent rather than replacing them.
Scope documents are revised during discussions, and the changes between versions are usually where the interesting questions are.
2.Testing where the work stops in each area
Most scope trouble happens at edges, not in the middle of rooms. Walk the boundary of the described work rather than reading down the page.
Walk each room holding the scope and work out where the described work stops on every wall, at the ceiling line and at the floor.
Reading a scope at a table describes an idea of the room; reading it standing in the room shows you the surfaces nobody mentioned.
Check what the scope says happens at each doorway between a room being worked on and one that is not, including the frame, the architrave and the floor covering either side.
Thresholds sit between two scopes and are frequently claimed by neither, which is obvious only once one side has been finished.
Note where decoration is described as stopping, and ask what happens where a newly finished surface meets an older one that is not being touched.
Whether an existing finish can be matched or joined into is a judgement for the trades involved; ask rather than assuming an invisible join.
Check whether the ground, paving, planting and boundary treatment around any external work are mentioned, and how far out from the building the scope reaches.
Ground disturbed by access, spoil and deliveries extends well past the described work, and the reinstatement of it is often unassigned.
Ask what the scope covers in rooms directly above and below the work, since disturbance, dust and service alterations rarely stay within one storey.
Ceilings below and floors above are affected by work that is described entirely in terms of a single room.
List every area the document states is excluded, and write down what you understand will be done there instead and by whom.
An exclusion says only that this document does not cover the work, not that the work is unnecessary; ask the appointed professionals what it needs.
3.The work between trades that nobody claims
Scopes are usually written trade by trade. The joins between them are where work quietly belongs to nobody.
List the items that need more than one trade to complete, such as a fitted unit that also needs power, water or extraction, and ask who owns each part.
Items requiring a sequence of visits are the ones most likely to be described once and assumed by everybody to be somebody else's complete responsibility.
Ask who is responsible for forming and making good openings where services pass through walls, floors and ceilings, and who decides where those openings go.
Where anything may pass through a structural element is a question for a qualified structural engineer and must never be settled on site alone.
Ask who prepares a surface for the trade that follows, and what standard of preparation the following trade expects to find.
Preparation is the classic unassigned task, because each trade assumes the other one either did it or will do it.
Check who fits, connects and commissions anything you are supplying yourself, and what the scope assumes about when those items will be on site.
Responsibilities for owner-supplied items vary between projects; ask the appointed professionals what is assumed about delivery, storage and fixing.
Ask who removes existing fittings, units and floor coverings that have to come out, and whether anything is to be set aside for reuse rather than discarded.
Items an owner intended to keep are removed as waste more often than any other single misunderstanding on a scope.
Ask who is responsible for coordinating the order in which trades arrive, and who tells you when a decision from you is holding that sequence up.
Coordination is a real task that is often assumed rather than assigned, particularly where trades are engaged separately.
4.What the scope assumes about the existing building
Every scope written before anything is opened up rests on assumptions. Getting them stated plainly now is far easier than arguing about them later.
Ask what the scope assumes is behind the surfaces that will be opened up, and get those assumptions written down in the document itself.
What lies behind a surface can only be established by opening it up; ask the appointed professionals how that is to be done and who attends.
Ask what the scope says should happen if conditions turn out differently from what was assumed, and who must be told before further work proceeds.
Deciding that a difference does not matter is a professional judgement; agree in advance who is contacted and who may call for work to pause.
Write down what you already know about the building from living in it, including damp patches, past leaks, uneven floors and areas that have been altered before.
Owner knowledge of the building is rarely asked for systematically, yet it is the most readily available source of information anybody has.
Note any part of the scope described as subject to survey or investigation, and ask who is arranging that work and what happens to the scope afterwards.
Whether an investigation is needed and what it should cover is a matter for qualified professionals, not something to settle from a scope document.
Ask what the scope assumes about the position of existing services, and who establishes where they actually run before anything is cut or lifted.
Establishing the route of existing services is specialist work; ask the appointed professionals and the relevant supply authorities what applies.
Ask what is assumed about the materials already in the building, and what the scope says should happen if something unexpected is uncovered.
Unidentified existing materials must be assessed by suitably qualified specialists; do not disturb, sample or describe them yourself.
5.Access, protection and living around the work
A scope that describes only the building work leaves out most of what an owner will actually experience. These arrangements deserve to be written down.
Check what the scope says about how the work is reached, which route is used through the property and which entrance is expected to be available.
Access through a hall, a garden or a neighbouring boundary changes what protection is needed and what an owner is agreeing to.
Ask what protection of floors, staircases, fittings and furniture is included, and who puts it in place, maintains it and takes it away.
Protection is often assumed to be included, and it is the first thing to disappear when a job is under pressure.
Write down which rooms you are expected to empty yourself and by what point, and where the contents are expected to go while the work is on.
Clearing rooms is almost always the owner's responsibility, and it is almost never stated in the document.
Ask what the scope says about interruptions to water, power and heating, how much notice you will be given and who tells you.
Isolating and restoring supplies is work for suitably qualified trades and the relevant supply authorities; ask who is arranging each one.
Ask what facilities the people working on site will use, including where they will wash, eat and take deliveries, and what that requires from you.
Where facilities are not described, the assumption is usually that the owner's property provides them, which is worth establishing early.
Ask how the property is to be secured at the end of each working period, who holds keys or access codes and who is responsible for locking up.
Security and insurance arrangements during work vary; confirm what is required with your own insurer and the appointed professionals.
6.Clearing away and the state you get back
The end of a scope is described in a sentence or two and matters enormously. Read those sentences more slowly than the rest.
Ask what the document means by leaving the property clean and clear, and what standard of cleaning is actually included at the end of the work.
Builder cleaning and the cleaning an owner imagines are two different things, and the gap is discovered on the last visit.
Ask who removes waste and packaging, where it is stored in the meantime and how often it is taken away during the work.
Waste removal is subject to local requirements that vary; confirm what applies with the relevant local authority and the contractor arranging it.
Ask what making good covers in each area, including whether it means patching a surface, refinishing a whole element or something in between.
Making good is the single most elastic phrase in a scope document and means something different to almost everybody who reads it.
Write down what happens to items removed during the work, including anything you want kept, and where those items are to be stored in the meantime.
An item nobody was told to keep is treated as waste, and by the time this is noticed the skip has already gone.
Ask which documents, instructions and product paperwork are due to you at the end of the work, and whether the scope mentions them at all.
Which certificates or records apply depends on the work and local requirements; confirm with the appointed professionals and the relevant authority.
Ask how items still outstanding at the end are recorded, who lists them and how you are told when each one has been dealt with.
A list made by the person who has to complete it works differently from one made jointly, and it is worth knowing which you are getting.
7.How the scope changes once work has started
The scope you accept is not the scope you end up with. What matters is how a change to it gets written down.
Ask how any change to the scope is recorded, who writes it down and how you will know that the document you hold is no longer the current one.
Changes agreed in conversation and never written back into the scope are the reason two people can honestly disagree about what was included.
Ask who on each side is entitled to agree a change to the scope, and record those names so that nobody else assumes they can.
Who may vary agreed work is set by your contract; ask your own legal adviser to tell you what your particular arrangement actually says.
Keep the scope as it was originally agreed, unaltered, alongside any later version, so the difference between them can always be established.
Without the original, a revised document simply becomes the truth, and nobody can say what changed or when.
Record changes that take work out of the scope as carefully as those that add to it, including who suggested the removal and why.
Removals are agreed quickly, discussed briefly and remembered poorly, which makes them the harder half of the record.
Ask what else in the scope a proposed change affects, including trades that have not yet arrived and items already ordered.
Working out the knock-on effect of a change is a professional task; ask the appointed professionals to set out what it touches before it is agreed.
Arrange to read the scope again once the building has been opened up, and note which of its assumptions have now been tested and which still have not.
The scope written before anything was exposed is the version everybody keeps working from, long after it stopped matching the building.
Preparation
Documents and information to gather
Having these to hand usually makes the first conversation shorter and more useful.
- The scope of works exactly as issued, together with every earlier version you were sent
- Your own written brief or list of what you asked for, in the form you gave it
- The drawings the scope refers to, at the issue the writer says they used
- Any survey or investigation report already carried out on the property
- Notes of what you know about the building from living in it, including past leaks and alterations
- Any product information for items you intend to supply yourself
Records
Decisions to record before work begins
Write these down in your own words, with the date, so everyone is working from the same version.
- Which rooms and areas you will clear yourself, and where the contents will go
- Which existing items are to be kept and set aside rather than removed as waste
- Which parts of the property are to remain in use while the work is under way
- Who on each side may agree a change to the scope once work has started
- What you understand making good to mean in each area, and who confirmed it
Professional review
Questions to discuss with qualified professionals
Bring these to the relevant qualified professional, supplier or authority. Requirements vary by project and location.
- Which drawings and which issue of them was this scope written against?
- Which parts of the work are excluded, and what would need to happen for them to be covered?
- Who is responsible for the preparation each trade expects to find before starting?
- What does this document assume is behind the surfaces that are going to be opened up?
- What should happen, and who must be told, if conditions turn out differently?
- What protection of the property is included, and who maintains it during the work?
- What does making good cover in each area described here?
- How will a change to this scope be recorded and reissued once work is under way?
Blind spots
Commonly overlooked items
- Thresholds and doorways between an area being worked on and one that is not
- Preparation between trades, which each assumes the other has already dealt with
- Ground and planting disturbed by access, deliveries and spoil rather than by the work itself
- Rooms above and below the work, which are affected without being mentioned
- Existing items the owner intended to keep and nobody was told about
- Who provides washing, eating and delivery arrangements for the people working there
What this checklist does not do
- This checklist helps you read a scope document; it cannot tell you whether the work described is complete, sufficient or appropriate for your property.
- Assumptions about what lies behind existing surfaces must be tested by opening up under the direction of qualified professionals, never by an owner working alone.
- The contractual effect of scope wording, exclusions and change provisions is a legal question; take it to your own legal adviser rather than settling it in conversation.
- Waste, access and security arrangements are subject to local requirements that vary; confirm what applies with the relevant local authority and your own insurer.
More preparation
Related checklists
Inspiration
Related Ideas Library pages
Design directions to explore once the preparation is done.
Go deeper
Related Build Design Hub guides
Explanatory planning guidance behind the decisions on this page.
Project Documentation & Changes Checklists
Owner-side checklists for drawings, specifications, instructions, variations and records — keeping a project legible when something changes.
Browse all Documentation & Changes checklists →