Who this guide is for
- Self-builders and developers considering infiltration on a plot
- Owners told a soakaway is or is not possible and wanting to know on what basis
- Renovators adding hard surface where the existing arrangement infiltrates
- Anyone reading a drainage proposal that assumes water goes into the ground
- Readers preparing questions for a drainage or geotechnical designer
What the test is actually asking
The question is whether the soil will take water and at what pace, not whether a hole can be dug. The disposal is done by the soil rather than by the structure, so the test is an examination of the ground and the structure is designed around the answer.
That is also why a general soil description cannot stand in for it. The entity record is explicit that how a given ground accepts water is established by investigation on that site, and that no general account of a soil type substitutes for it.
Where and at what level the test was done
Two details make the difference between a test that means something and one that does not: where the test was carried out, and at what level relative to the structure that will actually be built. Ground varies across a plot, and the relevant layer is the one the infiltration face will sit in rather than the one nearest the surface.
Those are the first two questions the entity record puts to professionals, and they are worth asking in exactly that form, because a favourable result from the wrong position or the wrong depth reads identically to a useful one.
- Where the test was carried out relative to the proposed structure
- At what level relative to the finished infiltration face
- How many positions were tested across the plot
- What the results were at each, and how much they differed
Recovery rather than capacity
A void that has emptied fully behaves as intended; the same void, part full when the next event arrives, behaves like a smaller one. That is why an arrangement that performed through a dry summer can surcharge in a wet autumn with nothing having been altered.
It also explains why a larger void does not substitute for ground that accepts water slowly. Capacity delays a problem where recovery rate resolves it, and the two are not interchangeable however the drawing looks.
Variation across a year, not only across a site
Groundwater is the second variable. Where the water table rises seasonally, a void can fill from below and stop accepting at exactly the moment it is needed. Whether the seasonal range has been established, and whether the structure sits clear of it, is a separate question from the infiltration test itself.
A test taken in one season therefore does not describe the whole year. It describes the ground at that moment, which is useful and incomplete in the same breath.
What a favourable result does not license
A result showing that the ground accepts water says nothing about whether water may be introduced there. Discharging water into the ground can affect neighbouring land, foundations and slopes, and consent arrangements are determined by the relevant authority.
Nor does it settle position. Because the arrangement deliberately wets the ground around it, its separation from foundations, retaining structures, slopes and buried services is settled with the structural and geotechnical advisers rather than treated as a layout convenience. Shrinkable clays, made ground and sloping sites all react.
- It does not establish that discharge to ground is permitted here
- It does not settle separation from foundations, walls, slopes or boundaries
- It does not describe the seasonal high groundwater level
- It does not mean the ground will still accept water once the face has silted
The property that ages
The infiltration face silts up gradually and irreversibly, and it is the only surface in the arrangement that cannot be cleaned, replaced or even seen without excavation. Everything upstream exists to slow that process, so the working life of the arrangement is decided by choices about interception rather than about the void.
That makes two later questions part of the same decision: what intercepts sediment before the void, and who is expected to empty it. A test result describes the ground on the day it was taken; the interception arrangement describes how long that result stays relevant.
What follows if the ground says no
An unfavourable result is not a failure of the site, it is the answer that redirects the design. Where the ground will not take water readily, attenuation with a controlled outflow, conveyance to another destination, or a lined feature with an underdrain are the arrangements that remain available.
The records treat these as siblings rather than fallbacks. The test is what tells the designer which family of arrangements the site is in, and that is a more useful outcome than a number on its own.
Infiltration testing discussion checklist
- 1Ask where the testing was carried out relative to the proposed structure
- 2Ask at what level relative to the finished infiltration face
- 3Ask how many positions were tested and how the results differed
- 4Ask what season the testing took place in
- 5Ask whether the seasonal range of groundwater has been established
- 6Ask whether the structure sits clear of the seasonal high level
- 7Ask what separation from foundations, walls, slopes and services has been assumed
- 8Ask who confirmed that separation
- 9Establish whether discharge to ground is permitted at this location
- 10Ask what intercepts sediment before the void and who empties it
- 11Ask what happens to the design if the ground accepts less than assumed
- 12Keep the testing record with the property for whoever owns it next
Common mistakes to avoid
- Inferring acceptance from a general soil description for the area
- Testing near the surface when the structure will sit lower
- Testing in one position on a plot where the ground varies
- Reading capacity as a substitute for recovery rate
- Taking a dry-season result as describing the whole year
- Treating a favourable result as permission to discharge to ground
- Positioning the structure by layout convenience rather than by advice
- Leaving interception out and shortening the life of the face
When to involve a professional
- How a given ground accepts water is established by investigation on that site
- Recovery rate, not capacity, is the property that governs the design
- Discharging water into the ground can affect neighbouring land and structures
- Separation from foundations and retaining structures is a geotechnical question
- Requirements vary by location and project; verify with your professionals
Frequently asked questions
Questions readers ask about this topic
Why is recovery rate more important than the size of the soakaway?
Because a void only reconciles differing clocks: water arrives quickly and the ground accepts it slowly. A void that has not emptied before the next event behaves like a smaller one, so capacity delays a problem that recovery rate resolves.
One test came back well. Is that enough?
It describes the ground at one position, at one level, in one season. Ground varies across a plot and groundwater varies through the year, so how many positions were tested and at what level are worth asking before a favourable result is relied on.
Does a good result mean I am allowed to discharge to ground?
No. Whether discharge is permitted is a consent matter determined by the relevant authority, and it is separate from whether the soil would physically accept water. Both have to be answered before an infiltration approach can be relied on.
What happens if the ground will not take water?
The design moves to a different family: attenuation with a controlled outflow, conveyance to another destination, or a lined feature with an underdrain. The records treat these as siblings rather than fallbacks, and the test is what identifies which the site is in.
Keep reading