Who this guide is for
- Owners who have commissioned a site investigation and received a report they cannot read
- Self-builders deciding what scope of investigation to ask for
- Buyers offered a report prepared for a previous scheme or a neighbouring plot
- Owners of an existing building where movement has raised questions about the ground
- Anyone briefing a structural engineer who has asked what ground information exists
What the report is for
A ground investigation exists to turn the subgrade from an unknown into a described body. The subgrade is not placed by the works; it is found by them, so its composition, water content and variability are properties to be established rather than chosen. The report is the record of that establishing.
It is also the evidence trail. Every later decision, founding level, whether treatment is worth carrying out, whether a shallow foundation is even in the conversation, is made against what the report says, and a design that cannot name its ground information is designing against an assumption.
Boreholes and trial pits look at different things
A trial pit exposes ground in the round at shallow depth: you can see the material, the way it changes, obstructions and any fill, and you can see it in the position it actually occupies. A borehole reaches much further down but describes the ground only along a narrow line.
Neither is a substitute for the other, and the mix chosen is part of the investigation design. What a report can say about the depth of a soft layer and what it can say about how that layer varies across a garden are two different confidences drawn from two different methods.
- Trial pits: shallow, wide view, good for fill, obstructions and near-surface variation
- Boreholes: deep, narrow view, needed where the answer lies well below the surface
- Sampling and laboratory work: what turns a description into measured behaviour
- Groundwater observation: often the part with the longest tail, because levels vary seasonally
Coverage is the limitation, not depth
The common misreading is to worry about whether the holes went deep enough. The harder question is how far across the plot the investigation actually extends, because the point is made directly in the reference entries: ground can vary sharply over short distances, which is why investigation is site-specific.
A piling entry puts the same point as a question for professionals, asking how confident the design is in the ground between the investigation points. Every hole is a sample, and everything between the holes is inference. Knowing where the samples sat relative to your building line is part of reading the report.
A factual report and an interpretation are not the same document
Investigations commonly produce a factual account of what was found and, separately, an interpretation of what it means for a design. The first records observation; the second applies judgement, and the judgement is made for a particular structure on a particular layout.
That distinction becomes important the moment the scheme changes. Facts survive a redesign; an interpretation written for a different building may not, which is why an engineer will ask to see both rather than a summary of either.
Why a neighbour's report is not your ground
The subgrade entry states plainly that neighbouring sites do not indicate what will be found. A report from next door can be useful background, and it can shape the scope of your own investigation, but a foundation designed against it has been designed against ground nobody has tested where you intend to build.
The same applies to a report prepared for an earlier scheme on your own plot. It described the ground at a set of positions for a set of loads, and whether it still answers the question depends on where the new building sits and what it weighs.
What the report does not decide
It does not choose a foundation. It does not state a founding level for your building. It does not say a site is suitable or unsuitable in itself. Those are design determinations made by qualified professionals who read the report alongside the structure being proposed.
- Whether the soil changes volume with moisture, and what that means for founding level
- Whether ground gas was assessed, since that is a separate specialist exercise
- What the groundwater regime does through a year, not only on the day of the visit
- Whether anything on the plot has been filled, disturbed or previously built on
Keeping it, because it is evidence later
The strip foundation entry notes that once a trench is backfilled nothing can be seen again, so what was recorded is what is known. The investigation report is the first half of that record and the inspection of the open excavation is the second. Together they are what any future extension or claim is judged against.
Questions to ask about a ground investigation
- 1Ask who carried out the investigation and who interpreted it.
- 2Ask where each borehole or trial pit sat relative to the proposed building line.
- 3Ask what the investigation says about variability across the plot, not only about depth.
- 4Establish whether you hold the factual report, the interpretation, or both.
- 5Ask what was recorded about groundwater, and whether levels were observed over time.
- 6Ask whether any part of the plot was found to be fill or previously disturbed.
- 7Ask whether the soil is one that changes volume with moisture.
- 8Ask whether ground gas was assessed, and if not, whether it should be.
- 9Check whether the report was written for the scheme now being built.
- 10Ask what assumptions about the ground the current design depends on.
- 11Ask what would trigger a decision to investigate further, and who makes that call.
- 12Store the report with the foundation drawings and the record of the open excavation.
Common mistakes to avoid
- Looking for one number in the report that settles the foundation, when the document describes a body of ground rather than a value.
- Judging an investigation by how deep it went rather than by how far across the plot it reached.
- Relying on a report prepared for a neighbouring site, when ground can vary sharply over short distances.
- Reusing an interpretation written for an earlier scheme after the building has moved or grown.
- Treating a summary email as the report, when an engineer needs the logs behind it.
- Assuming groundwater seen on one visit represents the level through a year.
- Filing the report away separately from the foundation drawings it explains.
When to involve a professional
- Ground behaviour is established by investigation and interpreted by geotechnical professionals; nothing here substitutes for either.
- Whether an investigation is sufficient for a particular scheme is a judgement for the engineers designing against it.
- Ground gas assessment is a separate specialist exercise, and its absence from a report is not a finding about a site.
- This page contains no soil classification, bearing value or basis for assuming what is beneath any particular plot.
Frequently asked questions
Questions readers ask about this topic
Is a ground investigation always needed?
Whether one is appropriate for a given project is a judgement made by the designers, and the library notes it is especially relevant on sloped, wet, shrinkable-clay or previously filled sites. A foundation designed without ground information is designed against an assumption.
What is the difference between a factual and an interpretative report?
The factual report records what was found at each position. The interpretative report applies judgement to that material for a particular structure and layout. Facts survive a redesign; an interpretation written for a different building may not, so an engineer usually wants both.
How many holes should an investigation have?
That is part of the investigation design and depends on the site, the structure and what earlier information exists. The useful question for an owner is not how many, but where they sat relative to the building line and how much ground lies between them.
Can the report tell me whether my site has radon?
Only if ground gas was part of the scope. Whether gases are present, at what concentration and under what driving pressure is established by a site-specific ground gas assessment carried out by a specialist, which is a separate exercise from a geotechnical investigation.
Do I need to keep the report after the work is finished?
It is worth keeping. Once a trench is backfilled nothing beneath can be seen again, so the investigation and the record of the open excavation are the only evidence of what the foundation is bearing on when a question arises years later.