Who this guide is for
- Owners planning a new stair, a rooflight or a riser through an existing floor
- Self-builders setting out stair and service positions on a new floor
- Anyone proposing to enlarge an existing stairwell
- Owners of a building with manufactured floor units considering an alteration
- Anyone coordinating a riser position with a structural layout
The floor may be doing a second job
Horizontal action on a building — wind, the tendency of anything leaning to lean further, ground movement — has to be caught somewhere and steered. Floor and roof plates do the catching, gathering force over their area, and connections hand it into walls, braced bays or cores that take it down.
That arrangement is largely invisible once a building is finished. A wall resisting horizontal action looks like any other wall, and a plate doing the collecting looks like a floor. This is precisely why an opening is not a joinery matter: what is being cut may be part of a chain nobody can read from the room.
Where the opening sits matters as much as its size
The stability entry is explicit. A stairwell, a lift shaft or a new floor opening interrupts the plate that gathers force, and the remaining material has to carry it around the hole. Where an opening lies against a stability element it can cut that element off from the plate feeding it, which is how an alteration that appears modest can change the behaviour of a whole storey.
So the question to put is not only how big the opening is. It is what the opening sits next to, and whether anything is being separated from the thing that was feeding it.
Trimming redistributes onto three sets of members
Forming an opening does not remove load; it redirects it. Everything the cut members were carrying arrives at the trimmer, and the trimmer delivers all of it as a concentrated reaction into the members either side of the opening. That is why trimming affects three sets of members rather than one: the interrupted ones, the trimmer, and the ones alongside.
The entries add that the connections at each end of a trimmer carry concentrated loads, which is why hangers and similar connectors are commonly used rather than simple bearing, and that whether a small opening needs trimming depends on what it interrupts rather than on how it looks.
A stair lands on the member framing the hole
Where the opening is a stairwell, the member framing it may be doing two unrelated jobs at one position. Everything the flights have gathered arrives at the landing, and the landing hands it into the structure framing the opening — commonly to the trimmer, which at that moment is occupied with redistributing a floor around a hole in it.
An opening framed only to edge a floor is framed for the wrong thing there. Whether the trimmer has been assessed for the stair's reaction as well as for the floor members it carries is a question worth asking before the stair is ordered, not after.
Two of these floors close the decision before manufacture
In a precast plank floor, each unit spans on its own and its steel runs the length of it, so openings are formed by trimmer arrangements or by units made short. An opening is a design and manufacturing matter rather than something cut once the floor is down, and it is settled with the manufacturer before delivery.
In a composite metal deck floor the sheet spans continuously, so cutting through it interrupts the tension reinforcement of the slab as well as the formwork, and the framing has to reinstate both. That is why penetrations are located before the deck is set out rather than agreed with the services trades afterwards.
- Precast units: openings agreed with the manufacturer before the units are made
- Composite deck: penetrations located before the deck is set out
- Post-tensioned plate: every opening fixed before the pour
- Mass timber panels: openings part of the manufacturing information
Everything else the opening interrupts
An opening between storeys is also a breach in separation, which the entries treat as a design matter beyond the structural one. Trimming a stairwell interrupts the ceiling and any sealing line in the same place, which is why a floor opening is a structural, acoustic and detailing question together.
The entries also note where the consequence shows: deflection of a trimmer appears in the floor around an opening, commonly at a stairwell where it is very visible, and the dip follows the outline of the opening rather than the direction of the members.
What to settle before the layout is fixed
The useful order is to establish what the floor is, what it is relied on to do at that level, and by what date an opening position has to be final. In a site-built floor that date may be generous. In a floor made from manufactured units it has usually already passed by the time anyone asks.
Before an opening is formed in a floor
- 1Establish what this floor is and what it is relied on to do for stability at that level.
- 2Ask whether the opening interrupts a plate that gathers horizontal force.
- 3Ask what the opening sits next to, and whether it separates anything from what feeds it.
- 4Ask how load is intended to be carried around the opening.
- 5Ask whether the members alongside have been assessed for the load they will receive.
- 6Ask how the concentrated reaction is transferred at each end of the trimming member.
- 7Where a stair lands, ask whether the framing member was sized before or after the stair position was fixed.
- 8Establish whether the opening affects fire separation between storeys.
- 9Ask what happens to the ceiling and any sealing line where the opening interrupts them.
- 10Where the floor is made from manufactured units, ask when opening positions have to be final.
- 11Ask what temporary arrangement holds the structure while the alteration is made.
- 12Record the opening, its framing and its date with the building's structural information.
Common mistakes to avoid
- Treating an opening as a joinery matter, when the floor may be gathering horizontal force across its area.
- Assuming only the cut members are affected, when the members alongside pick up the redistributed load.
- Judging whether a small opening needs trimming by how it looks rather than by what it interrupts.
- Placing an opening hard against a wall that may be part of the stability arrangement.
- Fixing a stair position after the floor framing has been designed for floor loading alone.
- Agreeing an opening on site in a floor whose units were manufactured to a drawing.
- Forgetting that an opening between storeys is a breach in separation as well as in structure.
When to involve a professional
- Forming or enlarging an opening in a floor is structural alteration requiring qualified design.
- Whether a proposed opening affects the building's stability arrangement is a determination for a qualified engineer for that building.
- Cutting or forming openings in a manufactured floor changes how it spans and is not a matter to be settled on site.
- An alteration that appears local can change how a whole storey behaves, particularly where it touches a connection or a plate edge.
- Nothing here is a basis for deciding that a floor or an opening may be altered.
Frequently asked questions
Questions readers ask about this topic
Does a small floor opening need structural design?
Whether it does depends on what it interrupts rather than on how it looks. The entries make that point directly, and add that a floor may also be gathering horizontal force across its area, which an opening interrupts regardless of its size.
Why does the position of the opening matter so much?
Because where an opening lies against a stability element it can cut that element off from the plate feeding it. The entries describe that as how an alteration which appears modest can change the behaviour of a whole storey.
Can I cut an opening in a precast floor?
Openings in such floors are ordinarily formed by trimmer arrangements or by units made short, agreed with the manufacturer before delivery, because each unit spans on its own and its steel runs its length. Whether anything can be done afterwards is a question for the engineer and the maker.
Why is the floor dipping around my stairwell?
One pattern the entries describe is a member framing the opening deflecting under a load it was not carrying, with the dip following the outline of the opening rather than the direction of the members. Whether that explains a particular floor requires investigation by a qualified professional.
When does an opening position have to be final?
It varies by floor. In a site-built floor the date can be relatively late; in floors made from manufactured units, openings are part of the information issued before manufacture, and in a post-tensioned plate every opening is located before the pour.