Kicker
Explains the kicker as a position that fixes the line of the element above, and separates it from the projecting reinforcement it is commonly confused with.
Educational reference entry. What this element has to do, and whether any particular arrangement of it is adequate, depends on the whole assembly, the loading, the exposure, local requirements, the manufacturer's instructions and qualified professional design.
Overview
What a kicker is
When a wall or column is cast on top of a slab or base, the formwork for it has to start somewhere and has to start in the right place. A kicker is a short upstand of concrete, cast as part of the slab or base beneath, standing in the line of the element above. The formwork for that element is then set against the kicker rather than against a flat slab surface.
Its purpose is positional. It fixes the line of the wall or column while the earlier pour is being cast, when setting out is easiest to control, and it gives the formwork above something to sit against and be sealed to. That is also why a kicker is not merely a convenience: an out-of-line kicker puts the element above out of line, and a kicker that leaks at its junction with the formwork leaves the base of the wall poorly formed exactly where it meets the pour below.
Boundaries
How it differs from nearby elements
The distinctions that keep this entry from being a restatement of its neighbours.
- It is not a starter bar. The kicker is concrete that locates formwork; the starter is reinforcement that continues the steel into the next pour. They occur at the same place and in the same operation, which is why they are confused, but one positions the mould and the other carries force, and an element may have starters with no kicker at all.
- It is not an upstand in the weathering sense. That upstand carries a waterproofing or roofing layer up above a surface; a kicker's job is setting out, and it is normally buried by the element cast on top of it.
- It is not a separate element added to the slab. A kicker cast monolithically with the pour beneath is part of that pour, and one cast afterwards introduces a further joint plane — which is precisely why how it was formed matters.
Terminology
Common names and aliases
These names describe the same element. The library keeps one entry per component so that a trade term or a regional name never becomes a second, thinner page.
- stub
- upstand kicker
Dependencies
What it depends on
What has to be right elsewhere for this element to do its job.
- Being set out accurately, because the element above inherits its line and correcting that later means moving formwork or moving the wall.
- Being cast so that its own concrete is sound at the junction, since it sits at the base of the wall and forms part of the joint plane between the pours.
- The seal between it and the formwork above, as fluid concrete finds any gap at the base of a pour.
- The reinforcement passing through it, since a kicker occupies exactly the congested region where starters and wall steel come together.
Considerations
Topics that genuinely apply here
Subjects worth discussing about this element. These are discussion topics, never measured values, ratings or performance claims.
Setting out is the kicker's whole reason for existing, and any error in it is transferred directly to the element above and is expensive to correct once cast.
The face of the kicker is where the formwork above is closed. A rough, damaged or out-of-plumb kicker face makes that closure difficult exactly where it needs to be tight.
In an element relied on to resist water, the kicker sits at the joint plane between base and wall, so how it is formed is part of how that joint performs rather than a separate matter.
The kicker is not the mechanism of continuity between the pours; reinforcement crossing the plane is. Treating the upstand itself as the structural connection misreads what it does.
Materials
Commonly formed from
Material families this element is commonly realised in. This states common practice only — it is not a statement that any of these materials suits this component in a particular building, which depends on the whole assembly and on qualified review.
Assemblies
Building systems this element is met in
The role this component fills inside each assembly. A role describes what the element does there — it is not a statement that this component suits that system in any particular building.
Clarifications
Commonly misunderstood
- That a kicker is optional tidy-up. Where it is used, it is the physical record of the set-out of the element above, made at the moment that set-out was easiest to establish.
- That kicker and starter bars are the same arrangement under two names. One is concrete for position, the other is steel for continuity, and each can exist without the other.
Conversations
Questions for qualified professionals
Questions worth asking someone with the project in front of them. This page cannot answer them.
- Was the kicker cast with the pour beneath or separately, and what does that mean for the joint at this location?
- How was the set-out of the kicker established and checked before the concrete was placed?
- How is the formwork above sealed against the kicker at the base of the pour?
- If this element resists water, how is the joint at the kicker addressed in the design?
Go deeper
Related Build Design Hub guides
Planning guidance behind the decisions this element involves.
Preparation
Related planning checklists
Owner-side preparation before the conversation where this element comes up.
What this entry does not do
- This entry describes a position. It states no kicker height, no dimension, no tolerance and no method of construction, and no such value can be inferred from anything written here.
- Whether a kicker is used, how it is formed and what it has to achieve at a particular junction are matters for the designer and the temporary works designer for that structure.