Site Access Route Record Checklist
Help an owner walk and write down the actual route materials, vehicles and people will take to reach the work, so the constraints are known and recorded before anyone plans how the work will be reached.
7 sections · 42 planning prompts · educational owner-side preparation
https://www.builddesignhub.com/checklists/site-access-and-logistics/site-access-route-record · Build Design Hub — educational planning resource. Requirements vary by project and location.
Scope
What this checklist covers
The preparation ground these prompts walk through.
- Walking and recording the route from the public road to the work area
- Pinch points, gate openings and turning space described in observable terms
- Overhead obstructions and the ground surface along the route
- The carry route through an occupied building and its communal parts
- Stretches of route that belong to, or are shared with, someone else
- Turning the record into something a professional who has not visited can use
Audience
Who this checklist is for
- Owners whose property is reached by a narrow lane, shared drive or rear alley
- Owners in a flat or shared building where materials must pass through communal space
- Owners preparing information for professionals who have not yet visited the property
- Owners whose only way to the rear is through the house or across neighbouring land
Timing
When to use it
- Recording the access route before anyone is asked how they would reach the work
- Spotting a constraint that would change how material has to arrive at the property
- Preparing labelled photographs and notes for people who have not seen the property
- Noting where the route leaves your land and passes onto ground controlled by others
- Keeping a dated record of the route condition before any vehicle uses it
Limits
When it is not sufficient
This is general planning preparation. These situations need a qualified professional, and often the relevant authority.
- Deciding whether any vehicle, load or piece of equipment can use the route
- Establishing what the ground, paving or a cover beneath the route will bear
- Determining what permissions apply to using a shared, public or third-party stretch
- Settling whether a right of access exists over land you do not own
- Judging whether a structure or opening along the route could be altered
The checklist
Work through the sections
Tick the boxes on paper or on screen — nothing is stored, so print the page if you want to keep your marks.
1.From the public road to your boundary
The part of the route you do not own often decides everything else. Record it as you find it, in the order a driver would meet it.
Note exactly where a vehicle would leave the public road for your property, and whether that turn is made from a main route, a side street or a shared lane.
The turn off the public road is where most access problems begin, and it is the first thing anyone arranging a delivery will ask about.
Walk the approach and write down whether it is a made road, an unmade track, a shared drive or a footpath, and note who else uses it regularly.
The character of the approach affects what can be brought in and who else has to be considered while it is occupied.
Note where vehicles habitually park along the approach, and at which times of day the route is most constricted by them.
A route that looks open in the middle of the day can be effectively blocked at exactly the times work would be starting or finishing.
Record the condition of the crossing between road and property, including whether the kerb is dropped, cracked, sinking or shared with a neighbouring entrance.
The crossing is frequently in different ownership from the drive behind it, and damage there turns into a dispute very quickly.
Ask the relevant local authority what applies to the crossing serving your property before any change to it is planned or assumed.
Stand at the entrance and note what a reversing driver could and could not see, including a wall, hedge, bend or habitually parked vehicle in the way.
Sightlines at the entrance often decide whether a vehicle can be reversed in at all or has to be manoeuvred somewhere else entirely.
Photograph the approach from the road towards the property and from the property back towards the road, and keep both sets of images dated.
Two directions of view answer most of the questions a professional would otherwise have to make a visit to resolve.
2.Pinch points, gates and where a vehicle can turn
Every route has one place that governs it. Find that place and describe it in terms someone who has never been here can picture.
Walk the route and identify the single narrowest point, then describe what forms it on each side, such as a gatepost, a wall, a bay window or a planter.
The narrowest point governs everything that can reach the work, and describing what forms it is far more useful than a figure taken loosely.
Record every gate on the route, which way each leaf swings, whether it can be lifted off its hinges, and whether the posts are set into the ground.
Gates that can be taken off temporarily change the route entirely, and this is almost always discovered later than it should be.
Note where a vehicle could turn and where it would have to reverse the whole way, and mark the nearest place it could pull in to let something pass.
Whether a vehicle can turn shapes which arrangements are workable at all, and a long reverse is a constraint people need to hear about in advance.
Record every archway, barrier, low branch, canopy or overhanging structure a vehicle would have to pass beneath, and photograph each of them.
Overhead restrictions are the constraint owners forget, because they are effectively invisible when the route is walked on foot.
Ask the supplier and whoever runs the work what clearance their vehicles and loads need at each of these points; do not estimate it yourself.
Note every corner where a long load would have to swing, including anywhere it would pass over a neighbouring verge, planting bed or parked vehicle.
Corners are where damage to other people's property happens, and naming them lets the risk be discussed before anything arrives.
Note every step, ramp, kerb and change of level between the entrance and the work area, and whether any of them could be temporarily bridged.
Level changes decide whether material can be wheeled or has to be carried, which changes how much of it can arrive at once.
3.What lies under and over the route
The surface a load crosses matters as much as the space around it. Record what is there and leave every judgement about it to others.
Record what the route is surfaced with along each stretch, such as block paving, gravel, grass, a resin surface or bare ground, and note where it changes.
Different surfaces behave very differently under repeated loading, and the point where one surface meets another is often where damage starts.
Mark on a sketch every drainage cover, inspection chamber, gully and service box the route passes over, and photograph each one where it sits.
Covers set into a drive are routinely driven over by everyone without anyone ever having asked what sits underneath them.
Ask a qualified professional what should be established about any cover or chamber before heavy loads pass over or stand on it.
Note where the ground stays soft after rain, where water stands, and where a vehicle would leave ruts if it strayed off the made surface.
Ground that is perfectly firm in dry conditions frequently becomes the main access problem once the work is actually under way.
Write down anything you know or suspect lies beneath the route, such as a former tank, a soakaway, a lightwell, a cellar or a filled-in area.
Owners often hold knowledge about a plot that appears on no drawing at all, and that knowledge is only useful once it is written down.
Raise anything you suspect lies beneath the route with a qualified professional before any vehicle or load is planned across it.
Note any overhead line, cable or wire crossing the route or the area where a vehicle would stand, and photograph it from ground level only.
Overhead lines crossing a drive or garden are commonplace, and they are a matter for the service provider rather than for the owner.
Never approach, move or work near an overhead line. Ask the relevant service provider and a qualified professional what applies at your property.
Note which planting, edging, lighting or garden features sit close enough to the route that they would probably not survive repeated use.
Deciding in advance what is expendable is far easier than discovering afterwards that something you valued was flattened by a delivery.
4.The carry route inside the building
Once material is off the vehicle it still has to reach the work. Walk that stretch as though you were already carrying something awkward.
Walk from the entrance to the work area carrying something long and rigid, and note every point where you have to tilt it, turn it or set it down.
Physically walking the route with an awkward object finds constraints that no plan drawing will ever show you.
Record every stair turn, half-landing and low ceiling on the internal route, and note where a handrail, newel or radiator narrows the passage.
Stair geometry often decides whether a large item can reach an upper floor at all, and is a common reason a plan has to change.
Note which doorways on the route have leaves that can be lifted off, and which sit in frames or openings that form part of the structure.
Taking a door leaf off is straightforward; altering an opening is an entirely different matter, and the difference needs establishing early.
Ask a qualified professional before assuming any opening on the carry route could be temporarily enlarged or taken out.
Record what the floors along the internal route are finished with, and note which of those finishes are staying and would therefore need protecting.
A finish that is being replaced anyway can be treated very differently from one you intend to live with afterwards.
Note whether there is any alternative way into the work area, such as a rear door, a window opening, a garden gate or an external stair.
An alternative entrance often avoids the internal route entirely, and it is worth identifying before any arrangements are settled.
In a shared building, record the lift, stair and corridor the route uses, and note any restriction the managing party places on their use.
Communal routes usually carry rules about times, protection and who may use them, and those rules are made by other people.
Confirm with the managing party or freeholder what applies to moving materials through communal areas before anything is arranged.
5.Stretches of the route you do not control
Access frequently depends on land, surfaces or permissions belonging to someone else. Identify those stretches and treat every one of them as a question.
Mark on a sketch the point where the route leaves land you own, and note who you believe owns or maintains each stretch beyond that point.
Assumed access over a shared drive or a rear lane is one of the most common late surprises in a domestic project.
Ask a qualified adviser to establish what access rights exist over any stretch you do not own before arrangements come to depend on it.
Read any title or lease document you hold for wording about access, rights of way, shared drives and maintenance, and note exactly what you find.
Owners rarely read these documents until a disagreement starts, although the wording usually existed long before anyone needed it.
Note which other households, businesses or services rely on the same stretch of route, and how obstructing it would affect each of them.
Knowing who else needs the route makes it possible to arrange work around them rather than in front of them.
Photograph the condition of every shared surface, verge, kerb and boundary along the route before any vehicle uses it, and keep the images dated.
A dated record made beforehand is the simplest way to settle a later question about who caused damage on a surface nobody owns alone.
If part of the work could only be reached across a neighbour's land, write that down as an open question rather than an assumption, and raise it early.
A request to cross a neighbour's land lands far better raised early than when a working team is already waiting at the boundary.
Crossing someone else's ground is not something a working team can agree for you. Take it to a qualified adviser before the route depends on it.
Where the route would occupy a pavement, verge or roadway, note that clearly and confirm locally what applies before anything depends on it.
Rules for occupying public space vary considerably between localities and are not something any checklist can state on your behalf.
Occupation of a pavement or road is controlled by the relevant local authority. Confirm what applies to your street with them directly.
6.Matching the route to what actually has to arrive
A route is only adequate in relation to what has to travel along it. Pair the record with an honest list of the awkward items.
List the items you expect to be most awkward to bring in, such as glazing units, beams, a bath, sheet materials or fitted cabinetry, and note which are rigid.
Rigid items that cannot be tilted, split or reassembled are the ones the whole route has to be considered against.
Ask whoever is arranging materials what kind of vehicle each delivery normally arrives on, and record the answers alongside your route notes.
Suppliers often have more than one vehicle option, but only offer it when the constraint is known before the arrangement is made.
Note anything that may have to be lifted over a building, wall or fence rather than carried through, and mark where a lifting vehicle could stand.
Identifying this possibility early changes where material is stored and how the rest of the route is planned around it.
Any lifting operation is a matter for qualified professionals. Record the constraint and leave the method entirely to them.
Ask which items could be delivered in parts and assembled at the property, and record which of them cannot be split under any circumstances.
Whether something can be split is often the whole difference between a workable route and an impossible one.
Note where material could be set down between the vehicle and the work area if it cannot be carried the whole way in a single movement.
An intermediate setting-down point is frequently what makes an otherwise awkward route usable in practice.
Ask whoever is planning the work what your route rules out, and write the answer down as a constraint rather than treating it as a passing remark.
Turning the route into an explicit list of constraints stops the same conversation being repeated with every new person involved.
7.Putting the record into a form others can use
A route record is only worth making if someone who has never visited can follow it. Assemble it deliberately rather than as loose notes.
Draw a simple sketch of the route from the road to the work area, marking gates, corners, covers, level changes and the narrowest point.
A rough sketch communicates a route far better than any written description, and it takes very little effort to produce.
Label each photograph against a position on the sketch, so anyone reading it can tell where the image was taken from and which way it faces.
Unlabelled photographs of a route are close to useless to someone who has never stood in those positions.
Note when the record was made and what the weather and ground conditions were like, since both change what the route looks like considerably.
A route photographed in dry conditions can mislead badly if the work will actually happen while the ground is wet.
Write down which parts of the route you could not reach, see beneath or open up, and flag those as gaps rather than leaving them blank.
Flagged gaps get investigated by somebody; blank spaces get quietly assumed to be fine.
Send the route record to anyone being asked about the work before they visit, and ask what else they would want recorded while you are there.
Professionals asked in advance will usually name one or two things you would never have thought to photograph.
Update the record whenever something on the route changes, such as a gate being removed, a surface breaking up or a new restriction appearing.
A route record that is out of date is worse than none at all, because people go on relying on it without checking.
Preparation
Documents and information to gather
Having these to hand usually makes the first conversation shorter and more useful.
- A dated set of photographs covering the route from the public road to the work area
- A sketch of the route marking gates, corners, covers and the narrowest point
- Any title or lease wording about access, rights of way and shared drives
- Notes of what the local authority confirmed about the crossing and any public surface
- A list of the most awkward items expected, and whether each of them can be split
- Managing party rules covering the use of communal stairs, lifts and corridors
Records
Decisions to record before work begins
Write these down in your own words, with the date, so everyone is working from the same version.
- Which entrance will be used as the main way in for materials and for people
- Whether any gate, planting or garden feature on the route will be taken out while work happens
- Where material will be set down between the vehicle and the work area
- Which floor finishes on the carry route are being kept and must therefore be protected
- Whether an alternative opening will be used instead of the internal carry route
- Who is responsible for keeping the route clear and passable while work continues
Professional review
Questions to discuss with qualified professionals
Bring these to the relevant qualified professional, supplier or authority. Requirements vary by project and location.
- What kind of vehicle would you expect to arrive here, and can that be varied
- What does this route rule out that we ought to know about now
- What clearance do your vehicles and loads need at the overhead points I have marked
- What should be established about the covers and chambers the route passes over
- Which of the items being ordered could be delivered in parts and assembled here
- What protection would you put down on the shared surfaces along the approach
- What would you want photographed or recorded here before anything arrives
- How would the work be reached if the shared stretch of route became unavailable
Blind spots
Commonly overlooked items
- Overhead branches, cables and canopies that are invisible when the route is walked
- Vehicles parked along the approach at exactly the times work would be starting
- A drainage cover set into the drive that nobody has thought to ask about
- Gate posts set into the ground, so the gate cannot simply be lifted off
- The stair turn that quietly decides whether a large item can reach the upper floor
- The point where the route leaves land you actually own without any visible marker
- Ground that is firm in dry weather and impassable once it has rained properly
What this checklist does not do
- This checklist records what is there. It makes no judgement about what any vehicle, load, surface or opening can bear or accommodate.
- Nothing here tells you what may happen on the stretch of route beyond your boundary. Ask the relevant local authority about the crossing and the road.
- Assumed rights over a shared drive, lane or rear alley are the weak point in a record like this. Treat every one of them as unresolved until advised.
- Overhead lines, buried services and drainage chambers are matters for the relevant service providers and qualified professionals in every case.
More preparation
Related checklists
Inspiration
Related Ideas Library pages
Design directions to explore once the preparation is done.
Go deeper
Related Build Design Hub guides
Explanatory planning guidance behind the decisions on this page.
Site Access & Logistics Checklists
Planning the practical side of having work happen at a property — access, deliveries, waste, neighbours, protection and the record made before work starts.
Browse all Access & Logistics checklists →